Megha & KNR Win Bangalore-Vijayawada Expressway’s Contracts
Megha Engineering and Infrastructures Ltd (MEIL) and KNR Constructions Ltd. on Monday were declared as the lowest bidders for the civil construction work of 518 km Bengaluru – Vijayawada Expressway project’s packages 5, 6, 11, 13 and 14.
Megha Engineering scooped up 4 civil packages (P5, P6, P11 & P14) with a combined length of roughly 124 km, while KNR won 29 km P13 – all located in Andhra Pradesh.
This 6 lane access-controlled expressway will be built under Bharatmala Pariyojana (BMP) Phase 1 with a mix of brownfield-upgrade (36%) and greenfield (64%) routes. Its alignment will pass by Kadapa lending it the name of BKV Expressway.
National Highways Authority of India (NHAI) had invited tenders for their construction under Hybrid Annuity Mode (HAM) in October & November 2022 with a 730 day (2 year) deadline.
Technical bids were opened 2 weeks ago to reveal 8 firms had submitted a total of 30 bids for packages 5, 6, 11, 12, 13 & 14. Interestingly, financial bids for 25.50 km Package 12 (Polavaram to Marripudi) were not opened for reasons unknown to me.
Package 5 (32.70 km)
Scope: Nallacheruvu palli (Ch.96.300) to Yerragudipadu (Ch 129.000)
Estimated Cost: Rs. 803.15 crore
Firm | Bid (Rs. Crore) |
Megha Engineering and Infrastructures Ltd. | 819.21 |
G R Infraprojects Ltd. | 937.87 |
Dilip Buildcon Ltd. | 998.19 |
PNC Infratech Ltd. | 999.00 |
HG Infra Engineering Ltd. | 1033.11 |
Package 6 (31 km)
Scope: Yerragudipadu (Ch.129.000) to Audireddipalle (Ch.160.000)
Estimated Cost: Rs. 809.51 crore
Firm | Bid (Rs. Crore) |
Megha Engineering and Infrastructures Ltd. | 802.22 |
G R Infraprojects Ltd. | 909.97 |
HG Infra Engineering Ltd. | 916.11 |
Dilip Buildcon Ltd. | 987.80 |
PNC Infratech Ltd. | 1017.00 |
Package 11 (32 km)
Scope: Chandrasekharapuram (Ch.228.000) to Polavaram (Ch. 260.000)
Estimated Cost: Rs. 862.48 crore
Firm | Bid (Rs. Crore) |
Megha Engineering and Infrastructures Ltd. | 854.71 |
G R Infraprojects Ltd. | 934.97 |
Dilip Buildcon Ltd. | 1001.07 |
Dineshchandra R Agrawal Infracon Pvt. Ltd. | 1008.00 |
Package 13 (29.10 km)
Scope: Marripudi (Ch. 285.500) to Somavarappadu (Ch.314.600)
Estimated Cost; Rs. 692.48 crore
Firm | Bid (Rs. Crore) |
KNR Constructions Ltd. | 665.00 |
Megha Engineering and Infrastructures Ltd. | 701.20 |
G R Infraprojects Ltd. | 753.37 |
Dilip Buildcon Ltd. | 799.83 |
HG Infra Engineering Ltd. | 808.11 |
Package 14 (28.64 km)
Scope: Somavarappadu (Ch.314.600) to Muppavaram (Ch.343.240)
Estimated Cost: Rs. 711.11 Cr.
Firm | Bid (Rs. Crore) |
Megha Engineering and Infrastructures Ltd. | 704.71 |
KNR Constructions Ltd. | 767.00 |
G R Infraprojects Ltd. | 770.97 |
HG Infra Engineering Ltd. | 844.11 |
Dilip Buildcon Ltd. | 849.06 |

The lowest bids in each case were either below (P6, P11, P13, P14) or negligibly higher (P5) than NHAI’s estimate, so I expect NHAI to award contracts in the coming weeks without a long financial evaluation period.
The project’s 343 km greenfield section connecting Kodikonda, AP to Addanki, AP has been divided up into 14 civil packages. With this development, financial bids for 9 packages have been opened, technical evaluation is underway for 1, while bidding is underway for another 4 – see a list and their contractors/status here.
For more updates, check out the Expressway section or my Home Page! Sign up for free instant email notifications on new posts over here. Like this post? Get early-access to updates and support the site over here.
– TMRG
Good good!
Complete it before December 2025 !
Package 12 was opened today. I will email you bid results.
WHO HAS GOT IT
Hi , where is the office in kadapa where NHAI consultant seat for this project
We are working all types pilling works By TMR and Hydrolic Rig
Plz give me project details and project manager contact no
Cell 9414357325
7838956848
GMR Media: – In the 5th package of the construction of Megha Company in the construction of Bangalore Vijayawada National Highway NH-544G, earth work ted construction with good gravel from chainage 117-500 to 119 is to be done, while the soil with loose stones is being brought and filled and rolled. Stone should not be more than 40mm in soil. But the cultivators are bringing soil with big stones and making ted. Everywhere you look, there is soil with big rocks. And people are questioning that the National Highway Authority officials are not the quality control officials. It is a well-known fact that good soil should be trodden and watered and rolled, but it is a well-known fact that there is no place to just water and roll on Ted. If the tankers are just like toys, they will remain there till evening if someone comes and moves them. Even the common people are discussing that construction with thousands of crores will last for ten years if the quality of supervision is good