GRIL – Patel JV Wins Dibang MPP’s Contract in Arunachal Pradesh

This project doesn’t quite fit into the typical contract categories that I track, but I thought it deserved a post given its big-ticket size, importance and location😀 It also includes several, 17 to be precise, tunnels which I’m most interested in.

GR Infraprojects – Patel Engineering JV on Tuesday was declared as the preferred bidder for Dibang Multipurpose Project (Dibang MPP)’s Lot-4 after reverse auction.

This $3.9bn hydroelectric project in the Lower Dibang Valley District of Arunachal Pradesh will produce 2880 MW (12 x 240MW) of power and help mitigate downstream flooding in the state of Assam.

It will consist of a 278m tall concrete gravity dam (tallest in India when completed), 6 horse-shoe shaped head-race tunnels of lengths varying between 300m to 600m with 9m diameter, an underground power house, 5 diversion tunnels, and 6 tail-race of lengths varying between 320m to 470m with 9m diameter.

Location of Dibang MPP close to the India – China border – via NHPC’s tender docs

NHPC had invited bids for Lot-4’s construction in February 2020 with an estimate cost of Rs. 3530.99 crore and completion deadline of 86 months. Financial bids were opened on March 7 while the reverse auction was held on March 21.

Reverse Auction Bid Values

FirmBid (Rs. Crore)
GRIL – Patel JV3637.12
Larsen & Toubro (L&T)3648.70
Afcons – Jaypee JV3853.28
Megha Engineering & Infrastructures (MEIL)Didn’t Qualify for Reverse Auction
Hindustan Construction CompanyDisqualified in Technical Round

Lot-4’s Brief Scope: All works comprising head race tunnels including intake, pressure shafts, penstocks, power house & transformer cavern, tail race tunnels, pothead yard, adits etc.

Dibang MPP’s Layout – view large

GRIL – Patel JV’s reverse auction bid value was neglibily higher than NHPC’s estimate, so a contract should be awarded in the coming weeks.

While we’re on the topic of hydro-electric projects, in the past I wrote about a Herrenknecht tunnel boring machine passing factory acceptance tests (FAT) for Pakal Dul Hydroelectric Project (HEP) in Jammu & Kashmir – read all about it here.

For more updates, check out my Home Page! Sign up for free instant email notifications on new posts over here. Like this post? Get early-access to updates and support the site over here.

– TMRG

written by

Global traveler who prefers mass rapid transit

16 Responses to "GRIL – Patel JV Wins Dibang MPP’s Contract in Arunachal Pradesh"

  1. Dd says:

    Patel engineering has good experience in construction of dam as they are in construction of Subansiri dam. Still it is amazing that government had already invited bids for construction early and now construction will start by year end

    Reply
  2. AT says:

    Bro why do you like tunnels?

    Reply
  3. Kumar Rahul says:

    Strategically it’s a very important project. This would help controlling flood situation in Brahmaputra river and Assam.

    Also it’s a counter to China’s water threat.

    Reply
  4. Rahul says:

    Strategically it’s a very important project. This would help controlling flood situation in Brahmaputra river and Assam.

    Also it’s a counter to China’s water threat.

    Reply
  5. Vaibhav Parashar says:

    Government is doing fast development. India is growing very fast. Such kind of government is always required in power. So that India can rise at full pace.

    Reply
  6. Utpal Payeng says:

    HMV Driver post

    Reply
  7. Prashanta Das says:

    The largest hydro electric power project in India

    Reply
  8. Shubhojeet Banerjee says:

    Sir,

    My request is to start One Hydro Project Category as well. Hydro Projects are Booming in INDIA and in-depth knowledge of All project is very much required.

    Thanks in Advance

    Reply

Leave a Reply

Want to join the discussion?
Feel free to contribute!

Leave a Reply

Your email address will not be published. Required fields are marked *