Bids Invited for Bhopal Metro’s BH-04 Underground Contract

Madhya Pradesh Metro Rail Corporation Ltd (MPMRCL) on Monday invited tenders for the civil construction work of Bhopal Metro Purple Line’s 3.39 km underground tunnels and stations.

Underground package BH-04 will connect a ramp south of Sindhi Colony Station with a ramp west of Aish Bagh Crossing Station via 2 underground stations at Bhopal Junction Station and Nadra Bus Stand.

This is the first and only underground package in the 27.87 km Bhopal Metro Phase 1 project. This is the Purple Line’s 4th and final civil package to enter the bidding stage after packages BH-01 (AIIMS to Subhash Nagar), BH-06 (Subhash Nagar Depot) and BH-03 (Subhash Nagar – Aish Bagh Ramp and Sindhi Colony Ramp to Karond Circle where bidding is underway).

Package: BH-04

Brief Scope: Design Construction of Twin Tunnel Cut Cover Cross passages with OR without sump Ramps two UG Stations including Architectural finishing Water Supply Sanitary Installation and Drainage works in entire UG from CH 28375 to 31765 for Bhopal Metro

  • Deadline: 1274 days (3.5 years)
  • Estimated Cost: Rs. 892 crore
  • Bid Submission Deadline: July 10, 2023 at 4 PM
  • Technical Bid Opening: July 11, 2023 at 4:30 PM
Indicative route of Bhopal Metro’s underground section – view Bhopal Metro Phase 1 route map & information

MPMRCL will likely require the assigned contractor to deploy at least 2 tunnel boring machines (TBMs) for constructing 6 tunnels.

This contract will be financed by the European Investment Bank (EIB) through a €400 million (approx. Rs. 3584 crore) loan signed in December 2019.

For more updates, check out the Bhopal section or my Home Page! Sign up for free instant email notifications on new posts over here. Like this post? Get early-access to updates and support the site over here.

– TMRG

written by

Global traveler who prefers mass rapid transit

10 Responses to "Bids Invited for Bhopal Metro’s BH-04 Underground Contract"

  1. Gomes Clevin Clement says:

    So the scope of this Contract also include 2 Underground stn ? I was bit confused

    Reply
  2. H says:

    This is not the 3rd civil package , it is the 4th . A elevated viaduct contract was invited in April . Part Design and Construction of Elevated Viaduct, Six Elevated Metro Rail Stations viz Pul Bogda a Passenger Interchange station between Orange and Blue line Aishbagh Sindhi Colony DIG Bungalow Krishi Upaj Mandi and Karond and Two ramps between Chain

    Reply
  3. Dinesh says:

    Sir,
    What about KNPC 11 UG package ?
    Any idea?

    Reply
  4. Amit kumar says:

    Whom awarded to UG pacakge, today is 12 july. Pls update

    Reply
  5. Shubham singh says:

    Whom awarded to UG package, today is 19 july. Pls update

    Reply
  6. GULABRAI & SONS INF PVT says:

    Package: BH-04

    Brief Scope: Design Construction of Twin Tunnel Cut Cover Cross passages with OR without sump Ramps two UG Stations including Architectural finishing Water Supply Sanitary Installation and Drainage works in entire UG from CH 28375 to 31765 for Bhopal Metro

    project kab award hoga please any update

    Reply

Leave a Reply

Want to join the discussion?
Feel free to contribute!

Leave a Reply to Dinesh Cancel reply

Your email address will not be published. Required fields are marked *