Agra Metro’s TBM Shivaji Records 1st Breakthrough at Taj Mahal Ramp
Afcons Infrastructure – SAM India JV today celebrated the first breakthrough by their third tunnel boring machine (TBM) Shivaji (S-718C) for the 29.40 km Agra Metro Phase 1 project.
This refurbished Ø6.63m diameter Herrenknecht Earth Pressure Balance machine was commissioned in early August 2023 to build twin underground tunnels on 14.25 km Line-1’s 7.93 km RBS College Ramp – Taj Mahal Ramp section (Package AGCC-02).
For its first assignment, Shivaji bored and built a roughly 228m long tunnel for the up-line from Taj Mahal Station’s launch shaft towards the cut & cover ramp on Fatehabad Road. This ramp connects to Sam India’s Package AGCC-01 where trial runs are underway.
Uttar Pradesh Metro Rail Corporation (UPMRC) had awarded Afcons – SAM Consortium with this section’s Rs. 1819.79 crore civil construction contract in March 2022 with a 48 month deadline.
Their section from chainage 3630.000 to 11564.485 consists of twin tunnels connecting 7 stations at Taj Mahal, Agra Fort, Jama Masjid, SN Medical College, Agra College, Raja ki Mandi and RBS College.
Interestingly, the paint on Shivaji’s cutterhead barely came off – thanks to a short distance and easy soil profile to bore through.
Shivaji will now re-deployed to build the parallel roughly 228m long down-line tunnel. Looking at the breakthrough shaft area’s set-up, I reckon instead of turning the machine around – most likely it’ll be dismantled, transported, re-assembled and relaunched from Taj Mahal Station.
For more updates, check out the Agra section or my Home Page! Sign up for free instant email notifications on new posts over here. Like this post? Get early-access to updates and support the site over here.