Hillways – GRTC JV Wins Kanpur Ring Road Package 3’s Contract
Hillways Construction Company – Gour Road Tar Coat JV on Monday was declared as the lowest bidder for the civil construction work of 93.2 km Kanpur Outer Ring Road project’s Package 3.
This 6 lane greenfield expressway by National Highways Authority of India (NHAI) will link Sachendi, Ramaipur, Rooma, Chakeri Airport, Trans Ganga City and Mandhana at an estimated cost of Rs. 5,182 crore. It will also be connected to the under construction Lucknow – Kanpur Expressway near Amarsus village.
18.9 km long Package 3 lies in eastern Kanpur and includes 2 parts: (1) 17.45 km section connecting Ata village (Ch. 51.200) – Khudhgaon (Ch.68.650) with a 1.2 km long bridge over Ganga River, and (2) a 1.45 km Airport Link Road to Chakeri Airport.
NHAI had invited tenders for its construction in January 2023 with a Rs. 845.23 crore estimate and 900 day (2.46 year) deadline. Technical bids were opened on September 13 to reveal 12 bidders.
Hillways – GRTC JV and Ceigall were initially disqualified in the technical round as they failed to meet the tender’s conditions. I suspect they questioned their disqualification, presented evidence, and got admitted.
Financial Bid Values
Firm | Bid (Rs. crore) |
Hillways – GRTC JV | 612.50 |
IJM (India) Infrastructure Ltd. | 642 |
GPT Infraprojects Ltd. | 657 |
HG Infra Engineering Ltd. | 709.11 |
DCC Infra Projects Ltd. | 733.38 |
GHV (India) Pvt. Ltd. | 735.43 |
KCC Buildcon Pvt. Ltd. | 739 |
PNC Infratech Ltd. | 843.03 |
Rail Vikas Nigam Ltd. (RVNL) | 878.51 |
Patel Infrastructure Ltd. | 894.08 |
Ceigall India Ltd. | 900 |
Brief Scope: Development of 6 lane GF Ring Road (PckgIII) starts from 51.200 to 68.650 (Length 17.450kms) around Kanpur City and Construction of 4lane Airport link road (Length 1.45 km) at 62.090 of Kanpur ring road in UP on EPC mode
Hillways – GRTC JV’s bid of 612.50 crore was substantially lower than NHAI’s 845.23 crore estimate, so a contract should be awarded in the coming months.
With this development, financial bids for Packages 1, 3 & 4 have been opened – see a list of all Kanpur Ring Road’s packages and their status over here.
For more updates, check out the Expressway section or my Home Page! Sign up for free instant email notifications on new posts over here. Like this post? Get early-access to updates and support the site over here.
– TMRG
Sir bhopal metro kab shuru hogi
Priority Corridor should open in Q3-Q4 2024
Sir kanpur ring road ka work kb suru ho raha h ….I am interested for material supply
Gitti mohrang etc …plz contact 8851364755
Sir me structure bridge contructor hu with shuttering material mujhe kanpur ring road m work karne ka moka dijiyega.
Contact -9340320186
Camp construction ka work
Callme
I am civil construction,I am doing ,minor, mjr brigde in ganga expressway , if contractor required , please call me
Electric working