Delhi Metro Silver Line’s TBM DZ1123 Records Breakthrough at Kishangarh

Larsen & Toubro (L&T) on Saturday celebrated tunnel boring machine (TBM) DZ1123’s breakthrough at Kishangarh Station’s cross-over for Delhi Metro’s 23.622 km Silver Line (Line-10) which will connect Aerocity – Tughalakabad via 16 stations.

This was DZ1123’s first breakthrough and overall the 2nd breakhthrough for Delhi Metro Phase 4 project’s 6.51 km Package DC-09 (Kishangarh – Saket G Block) where a total of 4 machines will be deployed by L&T.

Locally known as TBM-2, this CRCHI Earth Pressure Balance machine was commissioned in April 2023 from Chhattarpur Station’s west-end and built a 1274m tunnel for the down-line in 8 months.

Photo by Sanjit Das

Delhi Metro Rail Corporation (DMRC) had awarded L&T with Package DC-09’s Rs. 1428 crore contract in March 2022 with a 42 month deadline.

Their 6.51 km section, with twin-tunnels in the middle of the Silver Line, will connect Kishangarh Station (chainage 5356.285) with a cut and cover ramp (chainage 11867.000) west of Saket G Block Station. It includes 4 stations at Chhattarpur (interchange with Yellow Line), Chhattarpur Mandir, IGNOU and Neb Sarai.

Alignment of Delhi Metro Silver Line’s Package DC-09 – view Phase 4 route map with all stations’ exact locations marked
Photo by Sanjit Das
Photo by Sandip Mandal

This is the second of what I estimate 10 breakthroughs planned in Package DC-09. DZ1123’s sister machine DZ1122 had recorded the entire line’s first breakthrough at the same shaft in November 2023. Here’s a snap of both machines together:

DZ1122 and DZ1123 – Photo by Sanjit Das

L&T’s 3rd TBM DZ1125 was lowered into Chattarpur Mandir Station’s shaft in November. I haven’t heard of it being commissioned so far.

For more updates, check out the Delhi Metro section or my Home Page! Sign up for free instant email notifications on new posts over here. Like this post? Get early-access to all updates and support the site over here.

– TMRG

written by

Global traveler who prefers mass rapid transit

One Response to "Delhi Metro Silver Line’s TBM DZ1123 Records Breakthrough at Kishangarh"

  1. Jay Kumar says:

    Good news indeed! Congratulations to the entire team. Looking forward for the commissioning of the route as per schedule.

    Reply

Leave a Reply

Want to join the discussion?
Feel free to contribute!

Leave a Reply

Your email address will not be published. Required fields are marked *