Bids Invited for Patna Metro’s Underground Contracts PC-05 & PC-06
It’s finally out! Delhi Metro Rail Corporation (DMRC) today invited bids for two underground tunneling contracts (PC05 & PC06) of Patna Metro’s Line-1 connecting Danapur Cantonment – Khemni Chak.
This approximately 8 km section of the 30.91 km Patna Metro Phase 1 project will connect Rukanpura Ramp and Mithapur Ramp via twin tunnels built by tunnel boring machines (TBMs).
Each package consists of 3 underground stations and comes with a 42 month construction deadline financed through a loan by Japan International Cooperation Agency (JICA). They’re the final of 6 civil construction packages (see list) of the entire project to enter the tendering stage.
Looking at the tender documents, I see a station earlier planned at Chanakya National Law University (CNLU) near Mithapur is no longer in the works.
Package PC-05: Vikas Bhawan – Mithapur Ramp
- Estimate: Rs. 1683 crore (unconfirmed)
- Stations: Vikas Bhawan, Vidyut Bhawan & Patna Junction
- Pre-Bid Meeting: January 12, 2024 at 11 am
- Bid Submission Deadline: February 13, 2024 at 3 pm
- Technical Bid Opening: February 14, 2024 at 3 pm
Brief Scope: Design and Construction of Twin Tunnel by Shield TBM, Tunnel by Cut & Cover, Underground Ramp at Mithapur and Three Underground Metro Stations viz. Vikas Bhawan, Vidyut Bhawan & Patna Station including Architectural Finishing, Water Supply, Sanitary Installation & Drainage Works of Stations on Danapur to Khemnichak Corridor of Phase-I of Patna MRTS
Package PC-06: Rukanpura Ramp – Vikas Bhawan
- Estimate: Rs. 1377 crore (unconfirmed)
- Stations: Rukanpura, Raja Bazar & Patna Zoo
- Pre-Bid Meeting: January 15, 2024 at 11 am
- Bid Submission Deadline: February 13, 2024 at 3 pm
- Technical Bid Opening: February 14, 2024 at 3 pm
Brief Scope: Design and Construction of Twin Tunnel by Shield TBM, Tunnel by Cut & Cover, Underground Ramp at Rukanpura and Three Underground Metro Stations viz. Rukanpura, Raja Bazar & Patna Zoo including Architectural Finishing, Water Supply, Sanitary Installation & Drainage Works of Stations on Danapur to Khemnichak Corridor of Phase-I of Patna MRTS
Patna Junction Station will serve as an interchange between lines 1 & 2. 14.05 km Line-2’s tunnels connecting to Patna Junction are under construction by Larsen & Tourbo as part of Package PC-03 awarded in December 2021.
Rukanpura Ramp of PC-06 will be connected to elevated package PC-04’s western section, which is under construction by YFC Projects – Montecarlo JV. Mithapur Ramp will be connected to PC-04’s eastern section, also under construction by YFC Projects – Montecarlo JV.
With this development, the only major tender notice pending is for the project’s rolling stock (train) contract. The publishing of PC-05 & PC-06’s notices, after the approval of JICA, is a good indication to me that the trains’ tender notice is also around the corner. Stay tuned!
For more updates, check out the Patna section or my Home Page! Sign up for free instant email notifications on new posts over here. Like this post? Get early-access to updates and support the site over here.
– TMRG
Do you know how many TBMs will be deployed?
PMRC’s preparatory document recommended 3 & 2 machines for PC-05 & PC-06. Per one of my sources, it’s now 4 & 3.
Let’s see what happens.