YFC – BBG JV Bids for Nagpur Metro Phase 2’s C-09 Contract
YFC Projects – BBG Infrastructure JV on Tuesday was declared as the only bidder to construct package C-09 of the 43.8 km Nagpur Metro Phase 2 project.
Package C-9 by Maharashtra Metro Rail Corporation Limited (MAHA-METRO) will be financed by a $200mn loan approved by the Asian Development Bank (ADB) in July 2024. Its scope involves the construction of 8 elevated stations on the Orange Line’s Reach-1A at Ashokvan, Dongargaon, Mohgaon, Meghdoot CIDCO, Butibori Police Station, MHADA Colony, MIDC KEC and MIDC ESR.
Construction for the viaduct interlinking these stations will be carried out via Package C-02 and GR Infraprojects (GRIL) was awarded its Rs. 903.53 crore contract in October with a scope that includes building a double-decker viaduct.
MahaMetro had invited bids for C-09’s contract in April 2024 with a Rs. 258 crore estimate and 2.5 year deadline.
Maha-Metro’s Brief Scope: Construction of Eight Elevated Metro Stations viz Ashokvan Dongargaon Mohgaon Meghdoot CIDCO Butibori Police Station MHADA Colony MIDC KEC and MIDC ESR in Reach1A of NMRP Phase2
Whether MahaMetro is satisfied or not with receiving just 1 bid remains to be seen. If they aren’t, then this package will will head to a retender. If they are, then YFC-BBG JV’s technical bid will be evaluated for the next steps in the tendering process.
Back in April, Enia Design was declared as the lowest bidder for these 8 station’s Detailed Design Consultant (DDC) as part of contract DDC-03.
See a list of all Nagpur Metro Phase 2 packages (civil & systems) and their status over here.
For more updates, check out the Nagpur section or my Home Page! Sign up for free instant email notifications on new posts over here. Like this post? Get early-access to updates and support the site over here.
– TMRG
Leave a Reply
Want to join the discussion?Feel free to contribute!