8 Bidders for Gurugram Metro HUDA – Cyber City Line’s General Consultant Contract
Eight firms today submitted bids for the General Consultant (GC) contract of Gurgaon Metro’s 28.5 km line connecting HUDA Millennium City Centre and Cyber City.
This new elevated corridor by Haryana Mass Rapid Transport Corporation Ltd. (HMRTC) will form a ring line and connect Gurugram and Old Gurugram via 27 stations.
Its General Consultant contract is the second significant contract after the Detailed Design Consultant (DDC) contract where SYSTRA was declared as the lowest bidder in July after four rounds of bidding.
HMRTC had invited bids for the General Consultant contract in May 2024 and expects the consultant to stay on board for four years. The GC’s scope will include assisting HMRTC with design, supervision, safety, quality control and contract management.
Note: Some of the bidders mentioned below may be in a joint venture with other partners. If you’re aware of all members in each consortia, then drop a comment below or send me a message using the contact page.
General Consultant Bidders
- Aarvee Associates Architects Engineers & Consultants Private Limited
- AYESA Ingenieria y Arquitectura, S.A.U
- Consulting Engineers Group Ltd. (CEG)
- DB Engineering & Consulting GmbH
- Egis Rail SA
- Nippon Koei India Pvt. Ltd.
- SYSTRA MVA Consulting (India) Pvt. Ltd.
- TYPSA India Pvt. Ltd.
HMRTC’s Brief Scope: Appointment of General Consultants (GC) for metro line between Millennium City Centre and Cyber City
Besides an interchange with the Delhi Metro’s Yellow Line and Gurgaon’s Rapid Metro, Gurgaon’s new ring line will likely have an interchange with the 72 km Delhi – Dharuhera (RRTS) line at Cyber City and Hero Honda Chowk.
The GC’s appointment, like always, will be on the QCBS (Quality and Cost Based Selection) basis with a two stage (technical & financial score-based) process getting adopted for evaluating proposals.
The project was approved for construction by the Indian Government’s Union Cabinet in June 2023 and is experiencing obnoxiously severe delays even before construction begins which I see at this point starting no sooner than 2026.
For more updates, check out the Gurgaon Metro section or my Home Page! Sign up for free instant email notifications on new posts over here. Like this post? Get early-access to updates and support the site over here.
– TMRG
Plant and machinery department Sr Foreman my experience 27 years
DMRC 13 year experience
Present work L&T Construction
Bullet train project Ahmedabad to Maharashtra
Hey, Sir On which basis you are saying construction pf gurugram metro will start in 2026 . please tell your opinion and what should be done to begin fast construction ?
I agree with MRG because this is HMRTC. They will be finalizing the vendor in another 2-3 months (~Mar’25) and then that general consultant along design consultant will prepare a tender document which will take another 5-6 months (~Sep’25) and then finalizing of contractor will take not less than 5-6 months (~Mar’26). These are very ambitious timelines considering the history of HMRTC, GMDA and MCG, Gurgaon.
As we know 18 months have passed since the project was approved by the Govt in June 2023. We too agree that the work has delayed more than expected since nothing has happened on ground so far. Although it was promised to be completed by 2027..Let’s hope..the work progresses on ground soon, but once completed it’s going to be a game changer for everyone in Gurgaon. Lifeline and connectivity will be much smoother and comfortable. Let’s wish no more hurdles anymore. Have patience. ..With thanks and best wishes.
Its long pending and still delays which should not be accepatble. Govt should take concrete steps to fasten the process as Gurugram people are waiting and suffer daily due to traffic jams and all that stuff.
Hi TMRG,
What is the next step after GC appointment? After appointment of GC the tender for civil works can start right?
Everyone wants extension of yellow line but this chronic people don’t care about general public. They want their convenience and how they are benifitted. PMO is blocking everything which it can to connect dwarka sec 21 to gurgaon.
When start the work on ground of gurgaon metro . After declaration of this metro project many months waste.
Intention of State, centre Govt & HRMTC and other stake holder like MCG are in question as this much needes project of Gurugram Metro is pending since long. No positive sign in near future from all stakeholder. Worst 👎
We are eagerly waiting for extension of metro line from millennium city centre to old gurgaon.
Since July 23 it is flashing in news but in ground it had done nothing.
Year back the trees both side of proposed metro had cutdown that was a wrong decision.
After the piller work start it would have been done
It is too late now and waiting for ground breaking ceremony as soon as possible.
Jai Shree Ram.
surely it’s require for the time being. Further we need to plan town to avoid becoming like Mumbai..
I feel sorry to not available benefits of Metro extension till I retire in 2027
Sir,
What is the status update on the Dwarka sector 21 to Gurgaon metro, that will help decongest the Delhi Gurgaon to large extent and also help reduce the vehicular pollution as a lot of people transverse between these on daliy basis for work.
Worst chief minister of haryana. now worst urban development minister of india.manohar lal khattar
Right 👍 they have no plan for haryana
I don’t know why they put him in charge of that department given he’s barely done anything in that field in his previous work. Still, he was a way better CM in Haryana than the caste politics Hooda. You really think Congress would be any better in regards to metro development? Where have you been for the past decade?
Last 10 years we’ve been here Waiting for BJ Party to start the metro extension project
Yes they’ve been slow in Gurugram, but if you look at India as a whole it went from 250km of metro lines across 4 cities to 950km now across 16 cities, with 700km under construction right now and 1000km approved (And approved is 80% real this time, as opposed to Congress’s promise conversion rate to reality so another 800km or so should start construction in the next few years. We should hit 1700km by 2029 just based on what’s under construction and will start construction soon, and then maybe 2500km by 2034 if new starts keep up pace with the last few years.
No matter what time the project starts if anyone needs any Crane from 20 to 500 ton capacity for the Metro project, kindly contact me at at 9953048481. We are based in Delhi.
Any one aware about the Bhondsi Gurgaon metro line has this been approved or it was just a election announcement