KPC & URCC Bid for Bengaluru Suburban Rail’s Soladevanahalli Depot
KPC Projects Ltd. and URC Construction Pvt. Ltd. are the only two bidders for the construction of Soladevanahalli Depot of the 149.35 km Bengaluru Suburban Rail Project (BSRP) after Karnataka’s Rail Infrastructure Development Company (K-RIDE) opened technical bids on Monday.
Soladevanahalli Depot will be used to stable & maintain trains on 24.866 km Corridor 2 (Mallige Line) which will connect Baiyyappanahalli Terminal – Chikkabanavara via 14 stations. This depot along with another depot at Akkupet (Devanahalli) will house the project’s rolling stock comprising of 51 trains (306 coaches).
The contract’s scope also includes construction of a 1 km at-grade section between Chikkabanavara Station and Soladevanahalli Depot.
K-RIDE had invited tenders (bids) for its civil construction contract in September 2024 with a Rs. 170.93 crore estimate and 24 month construction deadline.
Tender No: K-RIDE/BSRP/DEPOT/SDHL/2024
KRIDE’s Brief Scope: Construction of Bangalore Suburban Railway Project (BSRP) Rolling Stock / Train Maintenance Depot with Administration & Workshop Buildings At Soladevanahalli (Chikkabanawara) including Civil, MEP, Roofing, Signage, Architectural Finishes, STP, External Drainage, Internal Roads, Boundary Wall, construction of At-Grade Formation of Length 1.00 Km (Approximately) and other Associated Works between Chikkabanavara Station to Soladevanahalli Depot of Bangalore Suburban Railway Project (BSRP).

Both bids have now been sent for technical bid evaluation which can take a couple months to complete. When that is done, the financial bids of the technically qualified bidders will be opened to reveal who’s the lowest bidder and most likely contractor.
A tender notice is currently pending for the construction of Akkupet (Devanahalli) Depot’s construction. A list of the project’s packages and their current status can viewed here.
For more updates, check out the Bengaluru Suburban Rail section, Bangalore Metro section or my Home Page! Sign up for free instant email notifications on new posts over here. Like this post? Get early-access to updates and support the site over here.
– TMRG
Track laying has been completed in MML 3 (Aqua line), can you provide more details for it?
Hi TMRG,
Please shed some light on this. We are waiting for your reply / post. 🙂
Hi TMRG
Any update on titagarh trainers for yellow line. As of now only one train is being tested.