GR Infra Begins Nagpur Metro Phase 2’s Work for Package C2
GR Infraprojects Ltd. (GRIL) in December-end officially started construction activities for Package C-02 of the 43.8 km Nagpur Metro Phase 2 project.
This major milestone was recorded roughly two months after Maharashtra Metro Rail Corporation Limited (MMRCL or Maha-Metro) awarded GRIL with Package C-02’s Rs. 903.53 crore contract with a 2.5 year deadline.
The scope of Package C-02 purely involves construction of a 17.624 km viaduct within Nagpur Metro Orange Line’s 18.7 km Reach 1A connecting Khapri – Butibori MIDC ESR. The construction of 8 elevated metro stations en route between Jamtha and Butibori will be carried out via Package C-09.
Reach 1A’s viaduct along NH-44 will consist of two special spans over the Indian Railways lines with lengths of 79m and 100m, and a 1.14 km long 6 lane double-decker section for vehicles (level 1) and CRRC metro trains (level 2).
Per GRIL’s construction plan, they will cast a total of 5144 segments and 746 PSC girders from 8 long-line casting beds and 16 short-line beds.
Here are some snaps GRIL’s casting yard at Tarsi Village where a bhoomi pooja was conducted:
This package’s construction will be financed by a $200mn loan approved by the Asian Development Bank (ADB) in July 2024.
Maha-Metro’s Brief Scope: Design and construction of elevated metro viaduct of length 17.624 km between ch.21256.814 to ch.38881.7 including railway spans of length 79m & 100m and 6-lane double-decker portion with vehicular underpass (vup) from ch. 25755.211 to 26895.211 for a total length of 1.14km in Reach-1A of NMRP Phase-2
This is the second section of Phase 2 and Orange Line where construction activities have started. D.P. Jain has since early 2024 been working on building 6.92 km Package C-01 of Reach 2A (Automotive Square – Kanhan River).
See a list of all Nagpur Metro Phase 2 packages (civil & systems) and their status over here.
For more updates, check out the Nagpur section or my Home Page! Sign up for free instant email notifications on new posts over here. Like this post? Get early-access to updates and support the site over here.
– TMRG
DMRC invited tenders for construction of viaduct from Saket g block to lajpath nagar with cost of 475cr.
Thanks – posted here: https://themetrorailguy.com/2025/01/07/bids-invited-for-delhi-metro-saket-lajpat-nagar-lines-contract-d2-c02/