Larsen & Toubro (L&T) on Monday poured concrete to cast their first set of 4 U-girders for the construction of Agra Metro Phase 1 project’s 15.09 km Line-2 which will connect Agra Cantonment – Kalindi Vihar via 14 elevated stations.

Work on L&T’s casting yard for Line-2’s construction, under Package AGCC-07, had started on November 27, 2024 – and this major milestone was recorded in just 2 months & 20 days, making this a new record for U-girder casting activities in India.

Their yard is located in Dauki village along Fatehabad Road (view satellite imagery on Google maps). Per L&T’s construction plan, they will cast 761 piers to build the line’s super-structure and launch 930 U-girders to form its viaduct.

Here are some snaps from the yard:

Uttar Pradesh Metro Rail Corporation (UPMRC) had awarded L&T with Package AGCC-07’s Rs. 1242.79 crore civil contract in November 2024 with a tight 24 month deadline.

Package AGCC-07’s scope includes the construction of the entire line’s viaduct, 14 elevated stations, 530m viaduct to Line-2’s Kalindi Vihar Depot, and interestingly a 2.61 km viaduct from north of Sadar Bazar metro station to Line-1’s PAC Depot built by Lisha Engineers as part of Package AGCC-03.

Map of Package AGCC-07 (Agra Cantt. – Kalindi Vihar) with key stations marked –  view Agra Metro Phase 1 route map & information

At Agra College Station users will be able to interchange and switch over to the city’s 14.25 km Line-1 (Sikandra – Taj East Gate) where an underground station is under construction by Afcons – SAM India JV as part of Package AGCC-02.

Last month, L&T cast their first pile cap (pier foundation) between Agra Cantt and Sadar Bazar stations, so things on Line-2 are moving extraordinarily fast even by UPMRC’s standards.

Line-2’s construction is being financed by the European Investment Bank (EIB) through a €450 million loan. See a list of all Agra Metro Phase 1 packages (civil & systems) and their status over here.

For more updates, check out the Agra Metro section or my Home Page! Sign up for free instant email notifications on new posts over here. Like this post? Get early-access to updates and support the site over here.

– TMRG

written by

Global traveler who prefers mass rapid transit

5 Responses to "L&T Casts Agra Metro Line-2’s 1st Set of U-Girders"

  1. Gomes Clevin Clement says:

    TMRG, who r the bidders of Mumbai Metro Line 5 Rolling Stock Tender?

    Reply
  2. BODHAN RUIDAS says:

    I am redi
    From work foreman 24yer experience From work Foramen

    Reply
  3. BODHAN RUIDAS says:

    Sir 🙏
    Iam redi From work Foramen
    24yer experience L&T

    Reply
  4. M/S Rubel Rana says:

    Civil contractor

    Reply
  5. ANURAG shukla says:

    I am ready for work in project’s

    Reply

Leave a Reply

Want to join the discussion?
Feel free to contribute!

Leave a Reply

Your email address will not be published. Required fields are marked *