Delhi Metro Phase 4 DC-01’s Final U-Girder Launched by CCECC – KEC JV
China Civil Engineering Construction Corporation – KEC International (CCECC – KEC) JV this week celebrated launching their final of 514 U-girders for Package DC-01 of Delhi Metro’s Line-8 (Magenta Line) extension project.
8.8 km Package DC-01 of the Delhi Metro Phase 4 project connects Mangolpuri – Haiderpur-Badli Mor in north-west Delhi via 7 elevated stations. This package combined with other civil packages – DC-01A, DC-03R, DC-05 and DC-06 will form a 28.92 km extension of Line-8 from Janakpuri West towards RK Ashram through 22 new stations.
CCECC – KEC JV had launched their first 165 ton & 28m long U-girder in November 2020 along Mangolpuri Flyover. This week’s final launch was recorded on top of piers P237-P239 at Madhuban Chowk along the Outer Ring Road.

Package DC-01 was originally designed to be 12.375 km long connecting Krishna Park Extension Ramp to Haiderpur-Badli Mor Station. Its Rs. 956.86 crore contract was awarded to CCECC – KEC JV in November 2019 with a tight 30 month construction deadline.
Construction work was launched in December 2019 wherever a clear right-of-way was available, but portions of the Krishna Park Extension Ramp – Mangolpuri section were held up for years due to pending permission approvals to cut trees enroute. After negotiations between CCECC – KEC and DMRC, this section was offloaded from DC-01’s scope and spun off into its own separate package (DC-01A) which was awarded to H.G. Infra Engineering (HGIEL) in January 2023.



DMRC on X today posted a cool photo of the Magenta Line’s 52.28m steel girders over the Indian Railways’ Delhi-Ambala line at Haiderpur Badli Mor (view on Google Maps). These girders at a height of 27.61m are flanked by the Yellow Line’s girders from Phase 3’s Package CC-02 at a lower level.

For more updates, check out the Delhi Metro section or my Home Page! Sign up for free instant email notifications on new posts over here. Like this post? Get early-access to updates and support the site over here.