Kochi Metro Phase 2 – Information, Route Maps, Tenders & Updates
Menu: News & Construction Updates | Fare Chart | Phase 1 Info | Phase 2 Info
Information
Kochi Metro’s Phase 2 project with one new 11.2 km Pink Line and 11 stations was approved by the Kerala Government in July 2018 with an estimated cost of Rs 2,310 crore.
Kochi Metro Phase 2 includes the construction of a spur line from Jawaharlal Nehru Stadium to Infopark II in Kakkanad. Its Rs. 1141.32 crore construction contract was awarded to Afcons Infrastructure in June 2024 with a tight 600 day construction deadline.
Kochi Metro Phase 2’s Detailed Project Report (DPR) was approved by India’s Central Government’s Cabinet in September 2022 with an estimated cost of Rs. Rs.1,957.05 crore
Phase 2 will partly be funded by Asian Infrastructure Investment Bank (AIIB) through a a $122mn loan approved in August 2024.
I expect Kochi Metro’s Phase 2 to be fully completed and opened by Q1 2028.
Kochi Metro Phase 2 Route
Line-2 (Pink Line): JLN Stadium – Infopark II
- Length: 11.2 km
- Type: Elevated
- Number of Stations: 11
- Station Names: Jawaharlal Nehru Stadium (new station box), Palarivattom Junction, Palarivattom Bypass, Chembumukku, Vazhakkala, Padamughal (formerly Kunnumpuram), Kakkanad Junction, Cochin SEZ (Special Economic Zone), Chittethukara, KINFRA (formerly Rajagiri), InfoPark 1 / Smart City 1, and InfoPark 2 / Smart City 2
- Status: Under Construction by Afcons Infrastructure since July 2024 (see details)
Kochi Metro Phase 2 Future Network Route Map
Kochi Metro Tenders
Latest Kochi Metro (KMRL) tender notices can be viewed on the KMRL’s website. News on these notices, their bidders, awarded tenders and contracts are covered in further detail on the news & construction page.
Kochi Metro Major Contractors
Contract | Contractor |
Detailed Project Report (DPR) Preparer | RITES |
Detailed Project Report (DPR) Revisor | Urban Mass Transit Company (UMTC) |
Project Management Consultant (PMC) | Tender cancelled (8 Bids Submitted in September 2021) |
General Consultant (GC) | SYSTRA S.A. – SYSTRA MVA Consulting (India) Pvt. Ltd. JV |
Detailed Design Consultant (DDC) for Station Components | Egis Rail |
Detail Design Consultant (DDC) for Power Supply And Distribution System, 750 V Dc Third Rail Traction Electrification And Scada System | SYSTRA MVA Consulting |
KBE-PC-01: Proof Consultancy Services For Power Supply Distribution System 750 V DC Third Rail Traction Electrification And SCADA System | Leap Infraasys Pvt. Ltd (LIPL) |
KBC-01-A: Balance/Additional works for the widening of Seaport-Airport Road from Kakkanad Signal Junction to Infopark Expressway Entrance | Deens Group is lowest bidder |
KBC-2: Road widening of JLN to Kunnumpuram Junction (CH. +50.00 to CH. 4550.00 | Winner Unknown |
KBC-3: Design and Construction of Elevated Viaduct and 10 Elevated Stations | Afcons Infrastructure |
KBC-4: Construction of entry exit buildings of Kakkanad JN and Cochin SEZ metro stations | Chendur Infrastructure Pvt. Ltd. |
KBC-05: Construction of Entry and Exit Buildings of Chittethukara, KINFRA PARK and Infopark Metro Station | Kool Home Builders |
KBC-06: Construction of Entry Exit Structure of Palarivattom Jn, Alinchuvadu, Chembumukku, Vazhakkala and Padamughal Metro Station | Tender Cancelled |
Click on ‘News & Construction Updates’ below for project news, progress and updates.