ITD Begins Work on Chennai Metro Line-4’s Underground Section
ITD Cementation has officially started pre-construction work at Marina Beach for Chennai Metro Line-4’s 10 km underground section connecting Power House Ramp – Light House Station.
Chennai Metro Rail Ltd (CMRL) had awarded ITD with the 118.9 km Chennai Metro Phase 2 project’s civil contracts for Packages UG-01 and UG-02 in January 2022 with a combined contract value of Rs. 3743.24 crore and 48 month deadline.
The firm has since mobilized men and machinery and started geotechnical soil investigation work to revalidate previous findings to help properly design and construct the line’s twin tunnels and stations.
This post deals with 5.15 km Package UG-01 (Bharathidasan Road Station to Light House) for which barricades and a geotechnical investigation rig was spotted near Light House Station’s site at Marina Beach.
This section includes 5 underground stations. ITD’s scope includes the construction of 4 of them at Bharathidasan Road, Alwarpet, Kutchery Road and Light House. Construction of Thirumayilai Station (interchange with Line-3) will be carried out through Line-3’s Package UG-04 which is being re-tendered right now.
Few images via @UpdatesChennai’s twitter handle – view more here.
The start of construction work for stations and tunnel boring machine (TBM) launch shaft is at least another 2 months away.
For more updates, check out the Chennai section or my Home Page! Sign up for free instant email notifications on new posts over here. Like this post? See how you can get early-access to updates and support the site over here.
– TMRG
Do you know any website for continuous work update of chennai metro phase 2 (like day to day)
May i know the requirements for daily day to day updates??? What was your profession!!???
Just a student who is enthusiastic about knowing the working of these huge projects😊
I am a civil engineer
I require a job
I am presently working in chennai
Please consider me in your project
I will do my best to the project
Searching for the same!!😅😅
Get ready to destroy the earth
Welcome boomer uncle
when will the work on Meenakshi college – Nandhanm streach wil commence?