SYSTRA Wins Kochi Metro Phase 2’s General Consultant Contract

SYSTRA S.A. – SYSTRA MVA Consulting (India) Pvt. Ltd. JV on Thursday emerged as the preferred & lowest bidder for Kochi Metro Phase 2’s General Consultant (GC) contract.

But there’s a twist to the tale. Kochi Metro Rail Ltd (KMRL) just hours ago (Friday evening) scrapped the tendering process as SYSTRA’s bid was significantly higher – by 59% – than their original estimate.

This consultancy contract by KMRL is the second significant pre-construction contract for Phase 2 which will feature a 11.2 km new elevated corridor, named Pink Line, with 11 stations connecting JLN Stadium – Kakkanad – Infopark (Smart City).

KMRL had invited tenders for it in November 2022 with a Rs. 31 crore estimate and expects the assigned GC to be onboard for 1095 days (3 years). Technical bids were opened in February to reveal 8 bidders.

SYSTRA on Thursday had won the contract based on the QCBS (Quality and Cost Based Selection) basis with a two stage process getting adopted for evaluating proposals. They scored the highest technical score and submitted the lowest financial bid.

Technical Bid Evaluation Results

FirmTechnical Score
SYSTRA JV85.72
Louis Berger JV85.50
AYESA – Aarvee JV78.77
DB – BARSYL JV74.77
TYPSA – STUP – PEMS JV72.00
PADECO – Altinok – Marsway JV56.00 (Disqualified)
MM – SMEC – PINI JVDisqualified
RINA – ICT JVDisqualified

Financial Bid Values

FirmBid (Rs. Crore)
SYSTRA JV49.57
Louis Berger JV52.98
DB – BARSYL JV59.99
TYPSA – STUP – PEMS JV68.95
AYESA – Aarvee JV86.11

Brief Scope: General Consultant (GC) for Phase- II Corridor from JLN Stadium to Infopark via Kakkanad of Kochi Metro Rail Project

Pink Line’s 11 stations will come up at Jawaharlal Nehru (JLN) Stadium (new station box next to Blue Line), Palarivattom Junction, Palarivattom Bypass, Chembumukku, Vazhakkala, Padamughal (formerly Kunnumpuram), Kakkanad Junction, Cochin SEZ (Special Economic Zone), Chittethukara, KINFRA (formerly Rajagiri), and InfoPark / Smart City (connected to Kochi Water Metro).

Route of Kochi Metro Phase 2’s Pink Line – view Phase 2 info & google-based map

With the tendering process cancelled, bids will have to be re-invited for the 3rd time with an adjusted estimate. This may take a while, so stay tuned!

Prior to this KMRL had appointed Delhi Metro Rail Corporation (DMRC) for Phase 1 (Aluva to Petta) and Aarvee Associates for Phase 1B (SN Junction to Thripunithura)’s PMC roles.

For more updates, check out the Kochi section or my Home Page! Sign up for free instant email notifications on new posts over here. Like this post? Get early-access to updates and support the site over here.

– TMRG

written by

Global traveler who prefers mass rapid transit

6 Responses to "SYSTRA Wins Kochi Metro Phase 2’s General Consultant Contract"

  1. Kartik says:

    I just don’t get this. Ok yes the bid was 58% higher but in real value it is not even 19 crores which is not that much.

    Considering this step delays the entire project by 6 months to a year, the increase in cost of cement, steel etc will surely be more than 20 crore for the project. This delay will cause a cost escalation of more than 29 crores.
    So isn’t it a sound financial decision

    Reply
    • Kartik says:

      Sorry accidently hit the publish button. A delete option would be really nice, just saying.

      Continuing,
      Isn’t paying 20 crore right now to get other contracts awarded asap be a better financial decision.

      As it is you can’t expect them to bid much lower in the next round so why delay everything else.

      As they say, this is the right time. Now is the cheapest time. Next time it will be more expensive.

      But then I get it, government stuff, regulations and so on which can’t be helped.

      Reply
      • TMRG says:

        “As it is you can’t expect them to bid much lower in the next round so why delay everything else.”

        Precisely! Agree with everything you’ve said above.

        Reply
    • Ebenser Chullikkatt says:

      Kochi metro has to take ratification from GoK. Normally the state government will take a call in the subject line. Otherwise the Consultant will go to Court.

      Reply
  2. Gomes Clevin Clement says:

    TMRG, is it true that Depot is now Finalise for Mumbai Metro Line 6 and Line 9 as per Tweet by Rajendra Sir
    https://twitter.com/rajtoday/status/1638964619258781696?t=oK2_9VyM-4qeUgtjYjlIsA&s=09

    Reply
    • TMRG says:

      That tweet contains what MMRDA’s chief said during a press meet. Might or might not be true. I’ll believe it when I see a tender notice getting published 🙂

      Reply