Ceigall India and its subcontractor Dixcon Infra this Thursday began casting pier caps for the viaduct of Package AGCC-05 on 14.25 km Agra Metro Line-1 connecting Taj East Gate – Sikandra.
Package AGCC-05 is a 3.725 km elevated section of 29.40 km Agra Metro Phase 1 project and will link RBS Ramp in Khandari and Sikandra via 3 elevated stations at ISBT, Guru Ka Taal and Sikandra – all located along national highway NH-19 (old NH-2).
By back of hand calculations, I estimate Ceigall will cast 110 pier caps – each with a width of 9.5m and weight of 62T.
Uttar Pradesh Metro Rail Corporation (UPMRC) had awarded Ceigall India with AGCC-05’s Rs. 266.94 crore construction contract in March 2024 with a tight 24 month deadline.
Package AGCC-05 is located on the northern-end of the line and is the third & final package for Line-1 main-line’s construction work. It will be connected to 7.93 km underground Package AGCC-02, and both twin tunnels between the Ramp and RBS College Station were recently completed by Afcons – Sam India Consortium in May.
In the coming months, Ceigall will start casting double-T girders for stations, and I-girders & U-girders for the line’s viaduct at their yard.
For more updates, check out the Agra section or my Home Page! Sign up for free instant email notifications on new posts over here. Like this post? Get early-access to updates and support the site over here.
– TMRG
Ceigall has been awarded LOA for Bhubaneswar metro BBC-05 recently as many have posted about it on Twitter, so please verify and update that information as well.
That’s correct – they received LOA. Will write about it when I get a copy of it.