Rahee Begins Mumbai Metro Line-9’s Track Work at Miragaon
Rahee Infratech on Thursday night began ballastless track casting activities for Mumbai Metro’s 11.38 km Line-9 which will connect Dahisar East and Mira Bhayandar through 8 elevated stations.
Standard gauge rails of 1435 mm under Package CA-167 will be installed by Rahee at the northern leg of the city’s new 31.05 km Red Line which will eventually connect Mira Bhayandar – Dahisar East – Andheri East – CSMIA Terminal 2 through 23 stations.
This elevated section is under construction by J Kumar Infraprojects via civil Package CA-48 since March 2020. The first U-girder to form Line-9’s viaduct, which includes several double-decker sections, was launched in April 2021.
Some snaps shot at Miragaon Station:
Mumbai Metropolitan Region Development Authority (MMRDA) had awarded Rahee with Line-9’s Rs. 77.85 crore track-work contract in March 2024 with a 1.5 year deadline.
Leena Powertech Engineers in July was declared as the lowest bidder for Line-7A and Line-9’s electrification contract CA-176, and at this point I reckon we’re easily another 2.5 years away from seeing both extensions of the Red Line getting commissioned.
For more updates, check out the Mumbai section or my Home Page! Sign up for free instant email notifications on new posts over here. Like this post? Get early-access to updates and support the site over here.
– TMRG
Hope it’s possible for mumbaikars go to in a train straight from mira-bhayendar to CSMT, instead of changing trains.
Yes it’s absolutely possible by end of 2026-27.
A person from Mira Bhayander can travel in metro via Line 9 (mentioned in above post), Line 7, 7A and then Line 3 without any hassle.
Interchange at Dahisar for L7 and T2 terminal for L3.
Mira-Bhayander to CSMT direct route is only by road in a private or personal vehicle. Everything else requires a change in the mode of transport.
v hope at earliest announce without date by fresh date change. our experience is “change date n fresh date” it’s not proper way in government system, change date with some reason.
greetings to all
yes. it is most awaited project and every new date means no commitment. just palying with sentiments.
India have multiple fields – Like – Renewal energy – Indian railways – NHAI – Irrigation – River linking project – New railway lines – Tunnels – water ways projects etc & Many more – It is requesting to update all sectors news 📰🗞️ mentioned above for an healthy updating systems –