Ahmedabad Metro Phase 2 – Information, Route Maps, Tenders & Updates

Menu: News & Construction Updates | Overview | Phase 1 Info | Phase 2 Info | Phase 3 Info

Phase 2 Information

28.254 km Ahmedabad Metro Phase 2 project with 2 corridors was approved by India’s Central Government’s Cabinet on February 19, 2019 at a total estimated cost of Rs. 5384.17 crores. Its foundation stone was laid by the Prime Minister Narendra Modi on March 4, 2019.

Phase 2 envisions a north extension of Line-2 from Motera Station to Mahatma Mandir in Gandhinagar. A notice inviting bids for its civil construction was published in January 2020, technical bids were opened in June 2020, and construction work started in February 2021.

A 20.8 km section of the 28.25 km Ahmedabad Metro Phase 2 project was inaugurated by PM Modi on September 16, 2024 connecting Motera – Sector-1 and GNLU-GIFT City (spur line).

Ahmedabad Metro Phase 2’s DPR (Detailed Project Report) in PDF format can be viewed here.

A roughly 5 km line connecting Koteshwar Road – Sardar Vallabhbhai Patel International Airport (spur of Red Line) was proposed to be included in Phase 2 plans, but has now been included in Phase 3.

Key Figures

Operational: 20.8 km | Under Construction: 7.45 km

  • GMRC’s Current Phase 2 Deadline: Not Revealed
  • My Completion Estimate: Q1 2026

Ahmedabad Metro Phase 2 Routes (Operational)

Line-2 (North-South / Red Line): Motera Stadium – Gandhinagar Sector-1

  • Length: 15.4 km
  • Type: Elevated
  • Number of Stations: 6
  • Station Names: GNLU, Raysan, Randesan, Dholakuva Circle, Infocity, Sector-1

Line-3 (Eastern Spur): Gujarat National Law University – Gujarat International Finance Tec-City (GNLU – GIFT City)

  • Length: 5.416 km
  • Type: Elevated
  • Number of Stations: 3
  • Stations Names: Gujarat National Law University (GNLU), Pandit Deendayal Petroleum University (PDPU) and Gujarat International Finance Tec-City (GIFT City)

Ahmedabad Metro Phase 2 Routes (Under Construction)

Line-2 (North-South / Red Line): Gandhinagar Sector-1 – Mahatma Mandir

  • Length: 7.45 km
  • Type: Elevated
  • Depot: Indroda (construction hasn’t started)
  • Number of Stations: 14
  • Station Names: Koteshwar Road, Vishwakarma College, Tapovan Circle, Narmada Canal, Koba Circle, Juna Koba, Koba Gam, Sector-10A, Sachivalaya, Akshardham, Juna Sachivalaya, Sector-16, Sector-24 and Mahatma Mandir

Ahmedabad Metro Phase 2 Route Map (By Line)

The embedded maps below shows the locations of all stations (Phase 1 – exact & Phase 2 – tentative) and can be zoomed into!

An official PDF route map of Ahmedabad Metro’s Phase 2 will be added here when available.

Ahmedabad Metro Phase 2 Route Map (By Phase)

Key: Phase 1 (Operational) | Phase 2 (Under Construction)

Project Video

Ahmedabad Metro Tenders

Latest GMRC Ahmedabad Metro Phase 2 tender notices can be viewed on the GMRC’s website. News on these notices, their bidders, awarded tenders and contracts are covered in further detail on the news & construction page.

List of Major Contractors

ContractContractor
GEC: Ahmedabad Metro Phase 2’s General Engineering ConsultantRITES – Nippon Koei – Oriental Consultants JV
DDC: Detailed Design Consultant for extension of Line-2 from Motera Stadium to Mahatma MandirSYSTRA – SYSTRA MVA Consulting (India) Pvt. Ltd. JV
DDC: Detailed Design Consultant for Power Supply & Distribution System, 750 V DC Third Rail Traction Electrification and SCADA SystemArdanuy Ingeniería S.A
Geotechnical Investigation: Line-2 Extn (Viaduct, 22 Stations & Depot)M K Soil Testing Laboratory
Civil Package C1: Viaduct from Motera to GNLU (8.124 km) and GNLU to GIFT City (5.420 km) with 10 stationsAfcons Infrastructure
Civil Package C2: Viaduct from GNLU to Gandhinagar Sector-1 (6.478 km) with 5 stationsRanjit Buildcon
Civil Package C3: Viaduct from Sector-1 to Mahatma Mandir with 7 stationsDilip Buildcon is lowest bidder
Rolling Stock Package RS3: 30 CoachesTitagarh Wagons
Signaling Package SIG-03: Communications based train control (CBTC)Nippon Signal – Nippon Signal India JV
Electrification Package EP2: 750 V DC Third RailSiemens – RVNL JV
Track-work Package: Design, Supply, Installation, Testing and Commissioning of Ballastless TrackVNC – KEC – Emrail JV
Tracks: 9116 MT of Head-Hardened RailsJindal Steel & Power Ltd. (JSPL)
Tracks: 788 MT UIC 60/60E1 R260 Grade RailsJindal Steel & Power Ltd. (JSPL)
Tracks: UIC 60/60E1 TurnoutsVoestapline VAE VKN India
Telecommunications System Package TEL-03Larsen & Toubro

Click on ‘News & Construction Updates’ below for project news, progress and updates.

Menu: News & Construction Updates | Overview | Phase 1 Info | Phase 2 Info | Phase 3 Info

Page last updated: September 17, 2024. Have a question or spot an error? Let me know here.