Nagpur Metro Phase 2 – Information, Route Maps, Tenders & Updates

Menu: News & Construction Updates | Phase 1 Info | Phase 2 Info | Broad Gauge Metro Project

Information

43.8 km Nagpur Metro Phase 2 project’s Detailed Project Report (DPR) was prepared by RITES and approved by the Maharashtra state government’s cabinet in January 2019 with an estimated cost of Rs. 5,976 crore.

In April 2023, Maharashtra government’s cabinet approved the project with a revised estimated cost of 6708 crore. The DPR’s approval has since then been pending on the Central Government’s cabinet for approval. The DPR document can be viewed on Maha-Metro’s website here.

Nagpur Metro Phase 2 will be financed by by Asian Development Bank (ADB) through a USD 200 Million (approximately Rs. 1678 crore) loan approved in July 2024. Additionally, the European Investment Bank (EIB) is currently evaluating another loan of €210.72 million (approx. Rs. 1943 crore).

Phase 2 project’s foundation stone was laid by Prime Minister Narendra Modi on December 11, 2022.

  • Nagpur Metro Phase 2 Deadline: 2026
  • My Completion Estimate: 2028-end

Nagpur Metro’s Phase 2 project aims to extend the two existing lines built in Phase 1 to Kanhan in the north, Butibori MIDC in the south, Transport Nagar (Kapsi) in the east and Hingna in the west. It comprises of a 1.2 km at-grade section with 2 stations and 42.6 km elevated sections with 30 stations

An additional 5th corridor is proposed to branch out from Line-2 at Vasudev Nagar towards Wadi, but has not been included in Phase 2’s official plan.

Nagpur Metro Phase 2 Routes

Line-1 (Orange Line) Reach 1A: Khapri to Butibori MIDC ESR

  • Length: 18.7 km
  • Number of Stations: 10
  • Station Names: Eco Park, Metro City, Ashokvan, Dongargaon, Mohgaon, Meghdoot CIDCO, Butibori Police Station, Mhada Colony, MIDC KEC and MIDC-ESR

Line-1 (Orange Line) – Reach 2A & Reach 2B: Automotive Square to Kanhan

  • Length: 13 km
  • Number of Stations: 12
  • Station Names: Pili Nadi, Khasara Fata, All India Radio, Kheri Fata, Lok Vihar, Lekha Nagar, Cantonment, Kamptee Police Station, Kamptee Municipal Council, Dragon Palace, Golf Club and Kanhan

Line-2 (Aqua Line) – Reach 3A: Lokmanya Nagar to Hingna

  • Length: 6.6 km
  • Number of Stations: 7
  • Catchment Area: Mount View, Rajiv Nagar, Wanadongri, APMC, Raipur, Hingna Bus Station and Hinga

Line-2 (Aqua Line) – Reach 4A: Prajapati Square to Transport Nagar

  • Length: 5.5 km
  • Number of Stations: 3
  • Stations: Pardi, Kapsi Khurd, Transport Nagar

Line-2 (Aqua Line) – Reach 5: Vasudev Nagar – Wadi

  • Length: 4.5 km
  • Number of Stations: 3
  • Catchment Area: MIDC Hinda, Pardsinga, and Wadi
  • Status: This extension has not been approved. It may be taken up in Nagpur Metro’s Phase 3.

Nagpur Metro Phase 2 Route Map (By Line)

Key: Line-1 – Orange Line | Line-2 – Aqua Line

An official PDF route map of Nagpur Metro Phase 2 will be added here when available.

Nagpur Metro Phase 2 Route Map (By Phase)

Maha-Metro has not released Nagpur Metro Phase 2’s official PDF route map. I’ll add it in here when available.

Key: Phase 1 | Phase 2

Tender Status & Contractors

ContractStatus/Contractor
Package DDC-01 (Reach 2A & 2B): Detailed Design Consultant (DDC) for 12 elevated stations between Pili Nadi – Kanhan RiverLKT Engineering Consultants
Package DDC-02 (Reach 3A & 4A): Detailed Design Consultant (DDC) for 8 elevated stations between Hingna Mountview – Hingna of Reach 3A and 3 elevated stations between Pardi and Transport Nagar of Reach 4AEnia Design – Mahendra Raj Consultants JV
Package DDC-03 (Reach 1A & 1B): Detailed Design Consultant (DDC) for 8 elevated stations between Ashokvan – MIDC ESREnia Design
Package DDC-04 (Reach 1A): Detailed Design Consultant (DDC) for at-grade section of Reach-1A for length of approx. 1669.417 M (CH. 19550 TO CH. 20421.016 and CH. 20498.516 to CH. 21296.917)Structcon Designs
Civil Package C-01 (Reach 2A): Design and Construction Of Elevated Metro Viaduct Of Length 6.92 Km Between Ch. (-) 657.182 M To Ch. (-) 7576.78 MRail Vikas Nigam Ltd. (RVNL)
Civil Package C-02 (Reach 1A): Design and construction of elevated metro viaduct of length around 17 km between Ch 21256 to Ch 38881 including Railway spans of length 79m and 100m and a 6 lane double decker portion with vehicular underpassGR Infraprojects Ltd. (GRIL)
Civil Package C-03 (Reach 3A): Design and Construction of Elevated Metro Viaduct of Length 6.414 km between Ch: 18218.586 m to Ch: 24633.194 mTender Cancelled (Scope absorbed into C-11)
Civil Package C-04 (Reach 4A): Design and Construction of Elevated Metro Viaduct of Length 5.333 km between Ch: (-) 289.668 m to Ch: (-) 5622.577 m in Reach-4ATender Cancelled (Scope absorbed into C-11)
Civil Package C-05 (Reach 1A & 2A): Construction of A) six elevated metro stations viz. Pili Nadi to Lekha Nagar in Reach-2A, B) one elevated and one at-grade station viz. Ecopark and Metro city in Reach-1A respectively. C) at-grade section formation earthwork, boundary wall and retaining wall between ch. 19550 to ch 20421.016 & ch 20498.516 to ch. 21296.917, D) elevated metro track supporting structure for ecopark metro station between ch.20421.016 to ch. 20498.516 and E) multi-storied building at tulsi school land (at sitabuldi)Rail Vikas Nigam Ltd. (RVNL)
Civil Package C-06 (Reach 3A & 4A): Construction of 7 elevated metro stations in Reach 3A (Hingna Mount View, Rajiv Nagar, Wanadongri, APMC, Raipur, Hingna Bus Station, Hingna) and 3 elevated metro stations in Reach 4A (Pardi, Kapsi Khurd & Transport Nagar)Rail Vikas Nigam Ltd. (RVNL) is lowest bidder
Civil Package C-07 (Reach 2B): Design and construction of elevated metro viaduct of length 5.9 km between ch (-)7577.056m to ch (-)13457.046mTender Cancelled (Scope absorbed into C-11)
Civil Package C-08 (Reach 2B): Construction of 6 elevated metro stations (Cantonment, Kamptee Police Station, Kamptee Municipal Council, Dragon Palace, Golf Club and Kanhan River Metro Station)Rail Vikas Nigam Ltd. (RVNL)
Civil Package C-09 (Reach 1A): Construction of Eight Elevated Metro Stations viz Ashokvan, Dongargaon, Mohgaon, Meghdoot, CIDCO Butibori Police Station, MHADA Colony, MIDC KEC, and MIDC ESR1 Bid Submitted in November 2024
Civil Package C-11 (Reach 2B, 3A & 4A): Design and Construction of Elevated Metro Viaduct for NMRP Phase-2 in I. Between Ch (-) 7577.056 m to Ch (-) 13457.046 m of length 5.9 km in Reach 2B II. Between Ch 18218.586 m to Ch 24633.194 m of length 6.414 km in Reach 3A III. Between Ch (-) 289.668 m to Ch: (-) 5622.577 m of length 5.333 km in Reach-4AKalpataru Projects International Ltd. (KPIL) is lowest bidder
Civil Package C-14: Civil Works of 2nd Entry-Exit structure and 100m Foot Over Bridge (FOB) connecting Cotton Market Metro Station in Phase 1’s Reach 4 SectionRadhakrishan Construction Co
Civil Package C-15: Widening of Nag River inside Krazy Castle area of NagpurC S Construction India Pvt. Ltd.
Electrical and Mechanical: E&M works of 12 stations on Reach 2 Extension and 2 DepotsColossus Infra Projects is lowest bidder (4 Bids Submitted)
Electrical and Mechanical (E&M-03): E&M works of 20 Nos. of stations in Reach-1, Reach-3 and Reach-4 ExtensionColossus Infra Projects
Elevators & Escalators: Lot-1 (Heavy Duty Machine Room Less Elevators), Lot-2 (Escalators) Tender Canceled in October 2024
Track Contract T-01: Ballasted track in at-grade section of Reach 1A including supply of 1080 Grade HH Rails, track fastenings, 1 in 9 R300 ballasted turnoutRahee Infratech is lowest bidder
Track Contract T-02: Ballasted-Ballast-less track in At Grade section of Reach 1A, and elevated viaduct of Reach 2A and Reach 4A2 Bids Submitted in November 2024
Telecommunications Contract TL-1: Phase 2’s Telecommunication systemSiemens is lowest bidder
Electrification Contract TR-02: 25kV flexible OHE and sectioning postsKEC International Ltd. is lowest bidder
Electrification Contract TR-03: Receiving cum auxiliary main cum traction sub stations including EHV connection from grid substation, 33 kv cable network, ASS and SCADA systemBNC Power Projects Ltd. (BNCPPL) is lowest bidder

Click on ‘News & Construction Updates’ below for project news, progress and updates.