Nagpur Metro Phase 2 – Information, Route Maps, Tenders & Updates
Menu: News & Construction Updates | Phase 1 Info | Phase 2 Info | Broad Gauge Metro Project
Information
43.8 km Nagpur Metro Phase 2 project’s Detailed Project Report (DPR) was prepared by RITES and approved by the Maharashtra state government’s cabinet in January 2019 with an estimated cost of Rs. 5,976 crore.
In April 2023, Maharashtra government’s cabinet approved the project with a revised estimated cost of 6708 crore. The DPR’s approval has since then been pending on the Central Government’s cabinet for approval. The DPR document can be viewed on Maha-Metro’s website here.
Nagpur Metro Phase 2 will be financed by by Asian Development Bank (ADB) through a USD 200 Million (approximately Rs. 1678 crore) loan approved in July 2024. Additionally, the European Investment Bank (EIB) is currently evaluating another loan of €210.72 million (approx. Rs. 1943 crore).
Phase 2 project’s foundation stone was laid by Prime Minister Narendra Modi on December 11, 2022.
- Nagpur Metro Phase 2 Deadline: 2026
- My Completion Estimate: 2028-end
Nagpur Metro’s Phase 2 project aims to extend the two existing lines built in Phase 1 to Kanhan in the north, Butibori MIDC in the south, Transport Nagar (Kapsi) in the east and Hingna in the west. It comprises of a 1.2 km at-grade section with 2 stations and 42.6 km elevated sections with 30 stations
An additional 5th corridor is proposed to branch out from Line-2 at Vasudev Nagar towards Wadi, but has not been included in Phase 2’s official plan.
Nagpur Metro Phase 2 Routes
Line-1 (Orange Line) Reach 1A: Khapri to Butibori MIDC ESR
- Length: 18.7 km
- Number of Stations: 10
- Station Names: Eco Park, Metro City, Ashokvan, Dongargaon, Mohgaon, Meghdoot CIDCO, Butibori Police Station, Mhada Colony, MIDC KEC and MIDC-ESR
Line-1 (Orange Line) – Reach 2A & Reach 2B: Automotive Square to Kanhan
- Length: 13 km
- Number of Stations: 12
- Station Names: Pili Nadi, Khasara Fata, All India Radio, Kheri Fata, Lok Vihar, Lekha Nagar, Cantonment, Kamptee Police Station, Kamptee Municipal Council, Dragon Palace, Golf Club and Kanhan
Line-2 (Aqua Line) – Reach 3A: Lokmanya Nagar to Hingna
- Length: 6.6 km
- Number of Stations: 7
- Catchment Area: Mount View, Rajiv Nagar, Wanadongri, APMC, Raipur, Hingna Bus Station and Hinga
Line-2 (Aqua Line) – Reach 4A: Prajapati Square to Transport Nagar
- Length: 5.5 km
- Number of Stations: 3
- Stations: Pardi, Kapsi Khurd, Transport Nagar
Line-2 (Aqua Line) – Reach 5: Vasudev Nagar – Wadi
- Length: 4.5 km
- Number of Stations: 3
- Catchment Area: MIDC Hinda, Pardsinga, and Wadi
- Status: This extension has not been approved. It may be taken up in Nagpur Metro’s Phase 3.
Nagpur Metro Phase 2 Route Map (By Line)
Key: Line-1 – Orange Line | Line-2 – Aqua Line
An official PDF route map of Nagpur Metro Phase 2 will be added here when available.
Nagpur Metro Phase 2 Route Map (By Phase)
Maha-Metro has not released Nagpur Metro Phase 2’s official PDF route map. I’ll add it in here when available.
Key: Phase 1 | Phase 2
Tender Status & Contractors
Contract | Status/Contractor |
Package DDC-01 (Reach 2A & 2B): Detailed Design Consultant (DDC) for 12 elevated stations between Pili Nadi – Kanhan River | LKT Engineering Consultants |
Package DDC-02 (Reach 3A & 4A): Detailed Design Consultant (DDC) for 8 elevated stations between Hingna Mountview – Hingna of Reach 3A and 3 elevated stations between Pardi and Transport Nagar of Reach 4A | Enia Design – Mahendra Raj Consultants JV |
Package DDC-03 (Reach 1A & 1B): Detailed Design Consultant (DDC) for 8 elevated stations between Ashokvan – MIDC ESR | Enia Design |
Package DDC-04 (Reach 1A): Detailed Design Consultant (DDC) for at-grade section of Reach-1A for length of approx. 1669.417 M (CH. 19550 TO CH. 20421.016 and CH. 20498.516 to CH. 21296.917) | Structcon Designs |
Civil Package C-01 (Reach 2A): Design and Construction Of Elevated Metro Viaduct Of Length 6.92 Km Between Ch. (-) 657.182 M To Ch. (-) 7576.78 M | Rail Vikas Nigam Ltd. (RVNL) |
Civil Package C-02 (Reach 1A): Design and construction of elevated metro viaduct of length around 17 km between Ch 21256 to Ch 38881 including Railway spans of length 79m and 100m and a 6 lane double decker portion with vehicular underpass | GR Infraprojects Ltd. (GRIL) |
Civil Package C-03 (Reach 3A): Design and Construction of Elevated Metro Viaduct of Length 6.414 km between Ch: 18218.586 m to Ch: 24633.194 m | Tender Cancelled (Scope absorbed into C-11) |
Civil Package C-04 (Reach 4A): Design and Construction of Elevated Metro Viaduct of Length 5.333 km between Ch: (-) 289.668 m to Ch: (-) 5622.577 m in Reach-4A | Tender Cancelled (Scope absorbed into C-11) |
Civil Package C-05 (Reach 1A & 2A): Construction of A) six elevated metro stations viz. Pili Nadi to Lekha Nagar in Reach-2A, B) one elevated and one at-grade station viz. Ecopark and Metro city in Reach-1A respectively. C) at-grade section formation earthwork, boundary wall and retaining wall between ch. 19550 to ch 20421.016 & ch 20498.516 to ch. 21296.917, D) elevated metro track supporting structure for ecopark metro station between ch.20421.016 to ch. 20498.516 and E) multi-storied building at tulsi school land (at sitabuldi) | Rail Vikas Nigam Ltd. (RVNL) |
Civil Package C-06 (Reach 3A & 4A): Construction of 7 elevated metro stations in Reach 3A (Hingna Mount View, Rajiv Nagar, Wanadongri, APMC, Raipur, Hingna Bus Station, Hingna) and 3 elevated metro stations in Reach 4A (Pardi, Kapsi Khurd & Transport Nagar) | Rail Vikas Nigam Ltd. (RVNL) is lowest bidder |
Civil Package C-07 (Reach 2B): Design and construction of elevated metro viaduct of length 5.9 km between ch (-)7577.056m to ch (-)13457.046m | Tender Cancelled (Scope absorbed into C-11) |
Civil Package C-08 (Reach 2B): Construction of 6 elevated metro stations (Cantonment, Kamptee Police Station, Kamptee Municipal Council, Dragon Palace, Golf Club and Kanhan River Metro Station) | Rail Vikas Nigam Ltd. (RVNL) |
Civil Package C-09 (Reach 1A): Construction of Eight Elevated Metro Stations viz Ashokvan, Dongargaon, Mohgaon, Meghdoot, CIDCO Butibori Police Station, MHADA Colony, MIDC KEC, and MIDC ESR | 1 Bid Submitted in November 2024 |
Civil Package C-11 (Reach 2B, 3A & 4A): Design and Construction of Elevated Metro Viaduct for NMRP Phase-2 in I. Between Ch (-) 7577.056 m to Ch (-) 13457.046 m of length 5.9 km in Reach 2B II. Between Ch 18218.586 m to Ch 24633.194 m of length 6.414 km in Reach 3A III. Between Ch (-) 289.668 m to Ch: (-) 5622.577 m of length 5.333 km in Reach-4A | Kalpataru Projects International Ltd. (KPIL) is lowest bidder |
Civil Package C-14: Civil Works of 2nd Entry-Exit structure and 100m Foot Over Bridge (FOB) connecting Cotton Market Metro Station in Phase 1’s Reach 4 Section | Radhakrishan Construction Co |
Civil Package C-15: Widening of Nag River inside Krazy Castle area of Nagpur | C S Construction India Pvt. Ltd. |
Electrical and Mechanical: E&M works of 12 stations on Reach 2 Extension and 2 Depots | Colossus Infra Projects is lowest bidder (4 Bids Submitted) |
Electrical and Mechanical (E&M-03): E&M works of 20 Nos. of stations in Reach-1, Reach-3 and Reach-4 Extension | Colossus Infra Projects |
Elevators & Escalators: Lot-1 (Heavy Duty Machine Room Less Elevators), Lot-2 (Escalators) | Tender Canceled in October 2024 |
Track Contract T-01: Ballasted track in at-grade section of Reach 1A including supply of 1080 Grade HH Rails, track fastenings, 1 in 9 R300 ballasted turnout | Rahee Infratech is lowest bidder |
Track Contract T-02: Ballasted-Ballast-less track in At Grade section of Reach 1A, and elevated viaduct of Reach 2A and Reach 4A | 2 Bids Submitted in November 2024 |
Telecommunications Contract TL-1: Phase 2’s Telecommunication system | Siemens is lowest bidder |
Electrification Contract TR-02: 25kV flexible OHE and sectioning posts | KEC International Ltd. is lowest bidder |
Electrification Contract TR-03: Receiving cum auxiliary main cum traction sub stations including EHV connection from grid substation, 33 kv cable network, ASS and SCADA system | BNC Power Projects Ltd. (BNCPPL) is lowest bidder |
Click on ‘News & Construction Updates’ below for project news, progress and updates.