4 Bidders for Nagpur Metro Phase 2’s Electrical & Mechanical Contract E&M-02

Four firms in December 2023 submitted bids for Electrical & Mechanical Contract E&M-02 of 43.8 km long Nagpur Metro Phase 2 project after Maharashtra Metro Rail Corporation Ltd. (Maha-Metro) opened technical bids.

The scope of Package E&M-02 includes work at 12 elevated stations of Aqua Line’s Reach 2 (Automotive Square to Kanhan) in eastern Nagpur. It also includes work at 2 depots, which I’m inclined to believe is expansion related and will take place within the existing depots built in Phase 1 at MIHAN and Hinga.

The 12 stations included within its scope will be built at Pili Nadi, Khasara Fata, All India Radio, Kheri Fata, Lok Vihar, Lekha Nagar, Cantonment, Kamptee Police Station, Kamptee Municipal Council, Dragaon Palace, Golf Club and Kanhan.

Maha-Metro had originally invited bids for this contract in July under package E&M-01 which was cancelled for reasons known to me. Bids were re-invited in November 2023 with Rs. 70.07 crore estimate and 900 day deadline.

Bidders

  • Colossus Infra Projects Pvt. Ltd.
  • Jakson Ltd.
  • Rail Vikas Nigam Ltd. (RVNL)
  • Univastu India Ltd.

MahaMetro’s Brief Scope: Supply, Installation, Testing and Commissioning of Electrical and Mechanical E AND M works of 12 Nos. of Stations in Reach 2 Extension and 2 Nos. of Depots under Nagpur Metro Rail Project Phase 2

Nagpur Metro Phase 2’s official map via MahaMetro

The bids are currently undergoing technical evaluation. When completed, the financial bids of the technically qualified bidders will be opened to reveal who’s the lowest bidder and most likely consultant.

The first of two contracts for the viaduct interconnecting these stations awarded to Rail Vikas Nigam Ltd. (RVNL) in September 2023.

A list of all Nagpur Metro Phase 2 civil & system packages and their status / contractors can be viewed here.

For more updates, check out the Nagpur section or my Home Page! Sign up for free instant email notifications on new posts over here. Like this post? Get early-access to updates and support the site over here.

– TMRG

written by

Global traveler who prefers mass rapid transit