Delhi Metro Phase 3 – Information & Map

Menu: Construction Updates | Overview | Phase 1 Info | Phase 2 Info | Phase 3 Info | Phase 4 Info

Phase 3 Information

Construction on the 159.327 km km Phase 3 of the Delhi Metro system began in 2011 and is currently underway. The first section opened in 2014 and the last section is expected to open in 2018.

This phase involves the construction of 2 new lines on standard gauge and the extensions of existing lines built in Phase 1 & 2.

New:
#7 – Pink lineMajlis Park – Shiv Vihar (58.596 km)
#8 – Magenta line  Janakpuri West – Botanical Garden (38.235 km)

Extensions:
#1 – Red lineDilshad Garden – Ghaziabad Bus Adda  (9.410 km)
#2 – Yellow line Jahangirpuri – Samaypur Badli (4.489 km)
#3 – Blue line – Dwarka – Najafgarh (4.295 km)
#3 – Blue line – Noida City Centre – Sector 62 (6.82 km)
#5 – Green line – Mundka – Bahadurgarh (11.182 km)
#6 – Violet line Central Secretariat – Kashmere Gate (9.370 km)
#6 – Violet line Badarpur – Ballabgarh (17.075 km)

Key for map below: Phase 1 | Phase 2 |  Phase 3 | Phase 4

List of Major Contractors

See this document: LIST OF CONTRACTS AWARDED FROM DMRC’s CONTRACTS SECTION

In addition, here are the signalling contractors:

Line Contractor
Line 7 (Pink) Bombardier Transportation
Line 8 (Magenta) Nippon Signal

History – Key Dates of Phase 3

26 Jun 2014: Central Secretariat – Mandi House (Violet Line) – 3.03 km
08 Jun 2015: Mandi House – ITO (Violet Line) – 0.972 km
06 Sept 2015: Badarpur – Escorts Mujesar (Violet Line) – 13.875 km
10 Nov 2015: Jahangirpuri – Samaypur Badli (Yellow Line) – 4.489 km