CMRL Invites Bids for Chennai Metro Line-1 UG Stations’ Balance Work

After terminating its Rs. 371 cr civil construction contract with IL&FS – PJSC Kyivmetrobud JV due to poor progress, the Chennai Metro Rail Ltd. (CMRL) on February 14 invited bids from construction firms for completing the remaining (balance) works of the underground Sir Theagaraya College and Korukkupet stations on the 9.051 km northern extension of Chennai Metro’s 23.1 km Blue Line to Wimco Nagar.

Both stations were originally part of package UAA-09, but now their balance works has been divided up into two separate packages. The tender notices are not yet up on CMRL’s website’s tender page, but a reader supplied copies –

CONTRACT BW-UAA-09- STATIONS (ARCH)/STC – CONSTRUCTION OF BALANCE WORKS OF CIVIL, ARCHITECTURAL BUILDING WORKS & FINISHES (ABWF), SIGNAGES ETC WORKS AT SIR THIYAGARAYA COLLEGE UNDERGROUND STATION.

Tender BW-UAA-09- STATIONS (ARCH)/SKP – CONSTRUCTION OF BALANCE WORKS OF CIVIL, ARCHITECTURAL BUILDING WORKS & FINISHES (ABWF), SIGNAGES ETC WORKS AT KORUKKUPET UNDERGROUND STATION.

• Duration of contract: 6 months
• Prebid meeting: 25-02-2020 at 11:00
• Last date submission: 13-03-2020 up to 15:00 hrs
• Date of opening Technical Bid: 14-03-2020 at 15:00 hrs

Route of Chennai Metro Blue Line’s 9.051 km northern extension which includes station package UAA09 with 2 stations at Sir Theagaraya College and Korrukupet – view Chennai Metro route map & information

At the time of termination, here’s what The Hindu reported

According to CMRL officials, they were left with no choice but to terminate the contract because they were displeased with the poor pace of construction. “Usually, we try to do everything possible to help the firm finish the work. We terminate contracts only if there is no other option. They [ITNL] struggled with severe cash crunch for several months and the progress of work was poor. Hence, we decided to end the contract recently,” an official said.

North of Korukkupet Station, the under construction line runs in an elevated mode with 6 new stations at Tondiarpet, Toll Gate, Thangal, Gowri Ashram, Tiruvottiyur and Wimco Nagar where an elevated stabling yard is being built, with further plans to build a 20 storey residential / commercial tower.

Track-work on the underground section has been completed and CMRL plans to run a diesel locomotive, like they typically first do, through the tunnels and maybe the elevated section if the tracks are ready towards the end of February prior to commencing trial runs with one of their Alstom trains.

For more updates, check out the Chennai section of The Metro Rail Guy!

– TMRG

written by

Global traveler who prefers mass rapid transit

3 Responses to "CMRL Invites Bids for Chennai Metro Line-1 UG Stations’ Balance Work"

  1. Kishore Kumar says:

    Always cancel the existing contractor and then work give to new contractor. Waste of time & money.
    Why not judge before giving to them??? Prevention is better than cure.

    Reply
  2. Anand Asir A says:

    CMRL has to think of what people actually expecting, not the show off things. Most of the deluxe buses are not stopping near Metro stations.
    St.Thomas Mount to Sozhilnganallur should be taken as priority corridor or phase 1 extension, knowing this connection will increase the ridership of Metro Phase 1. Low priority of corridor 5 making St.Thomas Mount to Adambakkam MRTS connection delayed as well because of multi modal construction plan.

    Reply

Leave a Reply

Want to join the discussion?
Feel free to contribute!

Leave a Reply

Your email address will not be published. Required fields are marked *