L&T Wins Delhi-Meerut RRTS’ Package 3 Contract

Larsen & Toubro has emerged as the lowest bidder for constructing the 32 km Duhai (EPE) – Modi Nagar North – Shatabdi Nagar section of the 82.15 km Delhi – Meerut Regional Rapid Transit System (RRTS) line, after officials from the National Capital Region Transport Corporation (NCRTC) yesterday opened financial bids.

NCRTC had invited tenders (bids) for Package 3’s civil construction in July 2019 with 2 sub-packages (lots) financed by the Asian Development Bank (ADB).

They estimated construction work of each lot to cost Rs. 860 crore and Rs. 1097 crore respectively. The second lot is the longer one and includes 2 stations at Partapur and Rithani which will also be a part of Meerut’s metro system.

Package 3 – Lot 1
DM/CN/COR-OF/058, LOT-P3L1: Construction of elevated viaduct from Duhai (EPE) to start of Modi Nagar North and 2 elevated stations viz. Murad Nagar & Modi Nagar South [excluding architectural finishing & preengineered steel roof structure of stations] of Delhi–Ghaziabad–Meerut RRTS Corridor

Lot-1’s route map: Duhai – Modinagar North – view NCR RRTS info & full map

Bid values submitted by each firm –

FirmBid
NCRTC’s EstimateRs. 860 cr
L&TRs. 784 cr
AfconsRs. 871 cr
NECRs. 969.74 cr
JMC1035.05 cr

Package 3 – Lot 2
DM/CN/COR-OF/059, LOT-P3L2: Construction of elevated viaduct from start of Modi Nagar North Station to Shatabdi Nagar Station and 5 elevated stations viz. Modi Nagar North, Meerut South, Partapur, Rithani & Shatabdi Nagar [excluding architectural finishing & pre-engineered steel roof structure of stations] of Delhi–Ghaziabad–Meerut RRTS Corridor

Lot-2’s route map: Modinagar North – Shatabdi Nagar view NCR RRTS info & full map

Bid values submitted by each firm –

FirmBid
NCRTC’s estimateRs. 1097 cr
L&TRs. 1014 cr
AfconsRs. 1115 cr
NECRs. 1235 cr
ITD CemDidn’t Qualify

If no issues arise, then in the coming days the NCRTC will go on to assign L&T as the contractor and award them with the line’s 3 & 4th major civil construction contracts.

The contract prior to this were awarded to APCO Infra – CRFG JV and KEC–CCECC JV for the 18 km ‘priority corridor’ section connecting Sahibabad – Ghaziabad – Guldhar – Duhai. Last week, they invited bids for the Sarai Kale Khan – New Ashok Nagar section – the civil package closest to the heart of the city.

For more updates, check out the NCR RRTS section of The Metro Rail Guy!

– TMRG

written by

Global traveler who prefers mass rapid transit

8 Responses to "L&T Wins Delhi-Meerut RRTS’ Package 3 Contract"

  1. Shreerang says:

    Any chance of this line opening before 2024?

    Reply
  2. vikash says:

    how can i contact for discuss the sub contract with them

    Reply
  3. Ajay Kumar says:

    Ajay Kumar civil engineering 2yerse experience Arvind tecno LLP mo9125182919 sir coll mi sir please

    Reply
  4. Deepak Dixit says:

    Good work

    Reply
  5. Ravi kumar says:

    Sir diploma in civil engineering fresher 2020 pass out 1st division se

    Reply
  6. Ravi kumar says:

    Sir diploma in civil engineering fresher 2020 pass out 1st division se

    Reply

Leave a Reply

Want to join the discussion?
Feel free to contribute!

Leave a Reply

Your email address will not be published. Required fields are marked *