RVNL Invites Bids for Kolkata Metro Line-3’s Mominpur Extension
Rail Vikas Nigam Ltd. today invited bids for the civil construction of Kolkata Metro Line-3’s Majerhat & Mominpur stations, a 1.326 km viaduct between them which includes a 50m steel girder span between piers P288-P289, and a small 225 meter viaduct ramp at Joka Depot.
Construction on Kolkata’s 16.5 km Line-3’s elevated part has been underway since 2011 by Simplex Infrastructures for 2 packages (4.748 km Joka – Behala and 4.762 km Behala – Mominpur), but work couldn’t earlier begin on Majerhat and Mominpur stations due to severe land acquisitions issues and pending approvals from the Indian Railways.
The construction of Majerhat Station, along with 2 others at Taratala and Behala Bazar was originally awarded to Gammon India in April 2012 under packages JMS-2. However, after the collapse of an adjacent 1960’s era Railway Overbridge (ROB) in September 2018, Gammon abandoned the Majerhat site due to design issues which has now led to re-tendering for its balance works.
Contract / IFB No: RVNL/Kol/Majerhat-Mominpur/Metro Work
Scope: Construction of Metro Railway Viaduct from P276 to P314 including Mominpur Station and Majerhat Station (Excluding PD Building and OCC Building side ) and Ramp at Joka depot end in connection with Joka-Esplanade Metro Railway Project in Kolkata, West Bengal
- Estimate: Rs. 190.64 crore
- Opening Date for Sale: 6/13/2020 12:00:00 AM
- Closing Date & Time for Sale: 7/27/2020 10:55:00 AM
- Opening Date for Download: 6/13/2020 12:00:00 AM
- Closing Date & Time for Download: 7/27/2020 10:55:00 AM
Station specs from the tender document –
Majerhat Station
- Length: 180m
- Number of Spans: 12
- Concourse Area: 3100 sqm
- Track Slab: 1880 sqm
- Platform Area: 3050 sqm
- Escalator: 5
- Lifts: 2
- Staircases: 5
Mominpur Station
- Length: 180m
- Number of Spans: 10
- Concourse Area: 980 sqm
- Track Slab: 1880 sqm
- Platform Area: 3100 sqm
- Escalator: 5
- Lifts: 2
- Staircases: 4
Things are looking up for this line. Back in April, RVNL invited bids for the construction of Joka Depot. In December 2019, bids were invited for appointing a Project Management Consultant (PMC) for its mostly underground 6 km northern extension from Majerhat to BBD Bagh to form a 3-line interchange at Esplanade Station. That tender has a closing date of June 29, 2020.
For more updates, check out the Kolkata section of The Metro Rail Guy!
– TMRG
Gammon was working on majherhat station they unable to complete it so maybe fresh tendering!
Thanks! I’ve added a blurb on Gammon for additional clarity
Any news on NewBarrackpore-Barasat Metro works tender opening?
Nothing at this time. Shoot me a mail or leave a comment if you hear anything.
Please edit a section….a ROB collapsed in September 2018,it was built in 1960s era.
Not under construction ROB
Thanks – have updated it!
According to performance only Afcons can did this on time. If they got.
Who got awarded the contract to build the Majerhat-Esplanade????
You haven’t published anything about it since this post…
Please enlighten me with the any kind of news you have regarding this.
Last date to submit PMC bids has been moved to 14/07/2020.
Tender opening to bid evaluation to contract award will take 6-12 months