Mumbai Metro’s TBM S-1074 Records Breakthrough at Dadar
Moments ago, Tunnel Boring Machine S-1074 (Krishna-2) operated by the Continental Engineering Corp – ITD Cementation – Tata Projects JV made a breakthrough at Dadar Station’s southern-end on Mumbai Metro’s 33.5 km Aqua Line (Line-3).
This was S-1074’s third (and final) breakthrough, 6.08 km Package UGC-04’s 7th of 8 planned breakthoughs for the Worli – Dharavi section, and overall Line-3’s 32nd of 41 planned breakthroughs.
This Herrenknecht TBM passed factory acceptance testing (FAT) in August 2017, and was commissioned in December 2017 to first build the 2472m down-line tunnel from Nayanagar Shaft to Dadar Station. After recording a double breakthrough along with its sister machine S-1073 in January 2019, it was recommissioned again from Nayanagar Shaft to build the 589m down-line tunnel towards Dharavi Station.
For its last assignment that ended today – the machine was dismantled and recommissioned from the other end of UGC-04 in December 2019 to build the up-line’s 1106 meter tunnel from Siddhivinayak Station to Dadar Station.
CEC-ITD Cem-TPL JV’s Package UGC-04 now has just 1 more breakthrough pending, also at Dadar Station for the parallel 1126 meter down-line tunnel. That breakthrough is expected to take place in December with another 520 meters or so more to go.
Here’s a table displaying UGC-04’s tunneling plan (best viewed on a desktop device) and the status of each tunnel –
TBM | Line | From | To | Distance | Status |
1 | Up | Nayanagar Shaft | Dadar | 2491m | Completed Jan 31 2019 |
1 | Up | Nayanagar Shaft | Dharavi | 589m | Completed Nov 21 2019 |
1 | Down | Siddhivinayak | Dadar | 1126m | In Progress |
2 | Down | Nayanagar Shaft | Dadar | 2472m | Completed Jan 1 2019 |
2 | Down | Nayanagar Shaft | Dharavi | 589m | Completed Oct 11 2019 |
2 | Up | Siddhivinayak | Dadar | 1106m | Completed Today! |
3 | Up | Siddhivinayak | Worli | 1305m | Completed Mar 15, 2019 |
3 | Down | Siddhivinayak | Worli | 1284m | Completed March 16, 2020 |
With 32 breakthroughs completed, there are now just 9 more breakthroughs pending on Mumbai Metro’s Line-3:
Package | Section | Distance, Status |
UGC-01 | Churchgate – Hutatma Chowk (up-line) | 650m, In Progress |
UGC-01 | Hutatma Chowk – CST (up-line) | 551m, Not Started |
UGC-01 | Churchgate – CST (down-line) | 1233m, In Progress |
UGC-03 | Science Museum – Mahalaxmi (up-line) | 1118m, Not Started |
UGC-03 | Mahalaxmi – Mumbai Central (up-line) | 837m, Not Started |
UGC-03 | Science Museum – Mahalaxmi (down-line) | 1136m, In Progress |
UGC-03 | Mahalaxmi – Mumbai Central (down-line) | 830m, Not Started |
UGC-04 | Siddhivinayak – Dadar (down-line) | 1126m, In Progress |
UGC-06 | Sahar Road – CSIA T1 (up-line) | 1516m, In Progress |
For more updates, check out the Mumbai section of The Metro Rail Guy!
– TMRG