L&T-STEC Restarts Mumbai Metro’s TBM Surya-1 towards CSMT
2020 had one last surprise in store!
Workers from Larsen & Toubro – Shanghai Tunnel Engineering Company (L&T – STEC) JV on Thursday recommissioned tunnel boring machine (TBM) XRE 2114-408 from Hutatma Chowk towards Chhatrapati Shivaji Maharaj Terminus (CSMT) for Mumbai Metro’s 33.5 km Line-3 (Aqua Line).
This Robbins Crossover XRE TBM, nicknamed Surya-1, had recorded a breakthrough in November for Package UGC-01 at Hutatma Chowk Station’s southern-end from Churchgate, and was then dragged to its northern-end through the 233 meter long station box using hydraulic jacks.
It has now been recommissioned on its 4th assignment towards CSMT (or CST) Station to build its final 551 meter long tunnel for Line-3’s up-line.
Mumbai Metro Rail Corporation (MMRC)’s Twitter handle shared this really nice video of the machine getting dragged, and then configured for launch with a view of the first temporary ring it started building:
With this development, here’s a status of package UGC-01 between Cuffe Parade and CST stations where 2 breakthroughs are pending, both at CST. This table is best viewed on a desktop device –
TBM | Line | From | To | Distance | Status |
1 | Up | Cuffe Parade | Vidhan Bhavan | 1128m | Completed |
1 | Up | Vidhan Bhavan | Churchgate | 498m | Completed |
1 | Up | Churchgate | Hutatma Chowk | 649m | Completed |
1 | Up | Hutatma Chowk | CST | 551m | Now in Progress (this post!) |
2 | Down | Cuffe Parade | Vidhan Bhavan | 1254m | Completed |
2 | Down | Vidhan Bhavan | Churchgate | 481m | Completed |
2 | Down | Churchgate | Hutatma Chowk | 653m | Completed |
2 | Down | Hutatma Chowk | CST | 556m | Yet to Begin |
The city now again has 4 active TBMs. 35 breakthroughs have been recorded so far (view last) and the following 7 are pending:
Package | Section | Distance, Status |
UGC-01 | Hutatma Chowk – CST (up-line) | 551m, Now in Progress (this post!) |
UGC-01 | Hutatma Chowk – CST (down-line) | 556m, Not Started |
UGC-03 | Science Museum – Mahalaxmi (up-line) | 1118m, In Progress |
UGC-03 | Mahalaxmi – Mumbai Central (up-line) | 837m, Not Started |
UGC-03 | Science Museum – Mahalaxmi (down-line) | 1136m, In Progress |
UGC-03 | Mahalaxmi – Mumbai Central (down-line) | 830m, Not Started |
UGC-06 | Sahar Road – CSIA T1 (up-line) | 1516m, In Progress |
For more updates, check out the Mumbai section of The Metro Rail Guy!
– TMRG
Compare with Kolkata line 2 tbm urvi had a breakthrough at sealdah on October 9 still sitting underground it retrieval shaft construction started on August7,was passing by that area another two months!