4 Bidders for Patna Metro’s Underground Construction Work

Four construction firms have submitted tenders (bids) to build the only underground package (PC-03) of Patna Metro’s 14.05 km Line-2 which will connect Patna Junction Railway Station and New ISBT through 12 stations.

After Phase 1’s Package PC-01 where NCC started piling work in December, the roughly 8 km package PC-03 is the second (and final) civil package of Line-2 and comprises of 6 underground stations. A station planned at Prem Chand Rangashala between Moin Ul Haq Stadium and University stations was dropped from the plans in 2020.

DMRC had invited tenders for PC-03 in September with an estimate of Rs 1958.81 crore and expects the assigned contractor to complete work in 42 months. Technical bids were opened today to reveal the following bidders.

Bidders (4):

  • Afcons Infrastructure
  • ITD Cementation India Ltd.
  • Larsen & Toubro (L&T)
  • Tata Projects Ltd. (TPL)

Package: PC-03

Brief Scope: Design and Construction of Twin Tunnel by Shield TBM, Tunnel by Cut & Cover, Underground Ramp at Rajendra Nagar and Six Underground metro stations viz. Rajendra Nagar, Moin Ul Haq Stadium, University, PMCH, Gandhi Maidan & Akashvani with Entry/Exits & Connecting subway including Architectural Finishing, Water Supply, Sanitary Installation & Drainage works on New ISBT to Patna Station of corridor-2 of Phase-I of Patna MRTS.

Patna Junction – Rajendra Nagar Ramp underground section – view Patna Metro information & route map

The bids have now been sent for technical evaluation which can take a couple months to complete. When that is done, the financial bids of the technically qualified bidders will be opened to reveal who’s the lowest bidder and most likely contractor for this package’s construction.

Financial bids for Package PC-04 (8 km, 7 stations) on Line-1 are expected to be opened soon, so stay tuned to find out its winner. That package received 4 bids back in November 2020.

For more updates on India’s metro systems, check out my Home Page!

– TMRG

written by

Global traveler who prefers mass rapid transit

23 Responses to "4 Bidders for Patna Metro’s Underground Construction Work"

  1. Rupraj Sengupta says:

    So approximately both the packages combined metro underground section will be roughly 16kms!

    Reply
  2. Samarth says:

    The first pillar of patna metro is complete or not

    Reply
  3. Anurag Kumar says:

    The bids have been sent for technical evaluation for Danapur cantt to pataliputra station how many more days will it requires to start final construction??

    Reply
  4. Vishal Kumar says:

    Which station of patna metro will be made terminal metro station??

    Reply
  5. Indra sen says:

    1)Any provision of PSD or PSG
    2) Train of both line line 1 and 2 will be same coloured and design or it may differ..
    3)what’s about rolling stock..
    4) what’s about the present status of line 1 first 6.1 km section??

    Reply
    • TMRG says:

      1. Nope
      2. Project is in early days
      3. Project is in early days
      4. Piling work is ongoing. If there’s any major update to share, I’ll post about it.

      Reply
      • TMRG says:

        For #2, to clarify – train design will be similar across all lines. Color is dependent on what PMRC wants for each. It’s one of those things where we’ll have to wait and watch.

        Reply
  6. Paras Sethi says:

    8 km w/ 6 stations is a very large package. This must be one of the biggest for metro construction in India.

    Reply
    • TMRG says:

      Yup! Closest in size are Delhi’s CC-23 (Hauz Khas – Kalkaji) and CC-27 (Shankar Vihar – Hauz Khas) in Phase 3.

      Reply
  7. Anurag Kumar says:

    Financial bids for Package PC-04 (8 km, 7 stations) on Line-1 are expected to be opened soon..Soon means this month or coming months..

    Reply
    • TMRG says:

      No one can provide a firm date or month, not even DMRC’s MD.

      Evaluation is nearing completion from what I hear. Will share results when announced.

      Reply
  8. Bhabishan singh says:

    Tbm worker cheye too contact me My number is 7596939353

    Reply
  9. Pavan says:

    General consultant?

    Reply
  10. Digvijay Pandey says:

    Store works

    Reply
  11. Saurav Kumar says:

    Any requirement of civil B.Tech degree holder sir. I am from patna.

    Reply
  12. Tejas says:

    By which time confirmation letter will be awarded for underground tunnel work will be awarded?
    Who’s chances are good?

    Reply
  13. Saurabh kumar says:

    Why tender not bid till time. Why so late?

    Reply

Leave a Reply

Want to join the discussion?
Feel free to contribute!

Leave a Reply to Rupraj Sengupta Cancel reply

Your email address will not be published. Required fields are marked *