Gulermak-Sam JV Wins Kanpur Metro’s Underground Contract
March 9, 2021 Update: Gulermak – SAM India has received UPMRCL’s LOA for Kanpur Metro’s underground contract with a combined value of Rs. 769.23 crore & USD 36.74 million
January 14 Original Post:
Moments ago, Gulermak – Sam India JV emerged as the lowest bidder among 6 firms to construct the first civil package of the 32.385 km Kanpur Metro Phase 1 project’s 8.621 km underground section, after Uttar Pradesh Metro Rail Corporation (UPMRC) opened financial bids.
Excluding the ramp, this package (KNPCC-05) of the 23.785 km Line-1 connecting IIT Kanpur – Naubasta has a length of 3619 meters and includes four stations at Chunniganj, Naveen Market, Bada Chauraha and Nayaganj – each 215 meters long.
UPMRC had invited tenders for this package on July 6, 2020 with an estimate of Rs 1400 crore and expects the assigned contractor to complete work in 36 months.
Technical bids were opened in September to reveal 7 bidders, and technical bid evaluation was completed last week in which 6 firms were shortlisted and Shanghai Tunnel Engineering Co. Ltd. was disqualified for not meeting the tender conditions.
UPMRC’s Estimate: Rs. 1400 crore
Financial Bid Values:
Firm | Bid |
Gulermak – Sam India JV | Rs. 1042.26 crore |
Tata Projects Ltd. (TPL) | Rs. 1179.08 crore |
Larsen & Toubro (L&T) | Rs. 1224.54 crore |
Afcons Infrastructure | Rs. 1231.05 crore |
JMC – CAI JV | Rs. 1259.31 crore |
Doğuş Construction | Rs. 1984.88 crore |
Tender No: UPMRC/CE-Contract/KNPRCC-05/2020
Package: KNPCC-05
Scope: Design and Construction of Tunnel from start of elevated ramp (after Motijheel Station) to end of Nayaganj station including four underground metro stations (viz. Chunniganj, Naveen Market, Bada Chauraha and Nayaganj) and ramp including Architectureal finishes, E&M, TVS, ECS etc. on Corridor-1 of Kanpur MRTS Project at Kanpur, Uttar Pradesh, India
Gulermak – Sam India’s bid of Rs. 1042.26 crore was well below UPMRC’s estimate of Rs. 1400 crore, so they should receive a Letter of Award (LoA) in the coming weeks.
This particular contract will be financed by the European Investment Bank (EIB) through a €650 million (approx. Rs. 5661 crore) loan approved in July 2020. When awarded, it will be Gulermak’s second underground contract in Uttar Pradesh. Back in 2016, they were awarded Lucknow Metro’s 3.44 km underground package LKCC-06 with 3 stations, which was completed in record time.
Tender notices for the line’s eastern section with 1 underground package (Nayaganj – ISBT) and 1 elevated package (ISBT – Naubasta) are still pending. A list of Kanpur Metro’s packages / contracts can be viewed viewed here.
For more updates on India’s metro systems, check out my Home Page!
– TMRG
That’s a huge difference between estimate and L1
True. I hear some folks calling it a suicide bid.
No it won’t, it will effect the work quality and compensation of JV employees
Hii
how is it possible nearly 400cr less than estimate this seems to be a problem. No quality would be mainted for sure.
Is it safe to award with such big difference between client and contractor. What if the contractor has bid a wrong tendering and later lifts his hands up due to loss.
If the difference was non-existent, there’s still no guarantee that contractors could pack-up and leave midway. Lots of examples across India.
The difference of 400 crore is too much.it points out that either estimates were wrong or the quality will be compromised.
Agreed. Negotiations with vendors (material / machines) will be aggressive as well.
Since the MD of UPMRC has mutual interest in the Sam India company, it is no surprise that Sam India is winning contracts for the elevated section of Agra Metro and underground section of Kanpur Agra
Noida metro also build by sam India
I want a job in metro work
2 year experience metro work
Mo.9005544828
Tell me more about this. I’m curious.
If you prefer, you can message me here: https://themetrorailguy.com/contact/
Do you know if it will be with slurry TBM?
No idea, but if I had to guess – EPB.
Negotiations with TBM vendors must have started now.
I’ll working for sullery tbm
TMRG do you have in your records any Tender before this for underground metro going so much below than client estimate or it is the first one ?
Unlike other tenders, UG metro tender requires huge investment in terms of equipment like TBM and highly specialized man power.
This is the first one with such a large difference. I’ve never seen anything like this.
Looking at the other bids, UPMRC clearly overestimated its value.
qc engineer vacancy
I would say the estimate was off because there are five bidders substantially lower than the estimate.
SAM has UPMRC’s MD in its pocket. They got L1 but till the end of execution phase, they will escalate their costs and get the variations sanctioned by the Competent Authority i.e. MD.
Kumar Keshav is not new in this shady business.
I don’t think they bid it wrong because on same time n same jv team bid Surat metro above the estimate time.
Secondly where gulmerk doing tunneling work going very smooth
. Lucknow metro then pune metro.
May be during pre bid some item get deleted from the station or change of scope..
Sam India type of company only works for money they never follow quality and if you see the quality of upmrc its like too bad they only care to complete the project in record time.
Sir,I’m current working in i dian railway track construction in southern railway through a private company ITC ltd,kanpilur
But i am more intrested in metro ,brdges,building and highway construction.
Hope for good quality work @kanpur metro
Dear sir I’m currently working itd cum JV MS work @ SS work @ Aluminium work Delhi DMRC CC 26R . But I’am interested in Matro Station MS .SS.@Aluminium work
dear sir i am currently working mmrc steel fixing work in sub contractor at j kumar infaproject limited please sir
Apply for job
Store in charge
All of respectives whoes working with sheild Tunnel boring machine in India have a requirement for segment casting for tunnel contact us on 9971009326. We have a lot experience for segment casting since 2006.we already work with (1) metro tunneling group (MTG) in DMRC project.(2) ALPINE.SAMSUNG HCC JV DMRC project. (3) NATM tunnel with ALPINE HCC JV in DMRC project.(4) segment casting in FEMC PRATIBHA JV at DMRC.
I worked in prtibha JV 2013
My current job dogus soma
TBM FORMEN my contact no
7974258106
Sir aapki company me JCB & Excavator poclain machine Ki requirement h kya available for rent basic and monthly payment contact me 9015327828,9451244112
Aply . Forklift operator
Telihandle op
Lifter op
Exp 9 yers metro
Contact 8610970538
Running job Mumbai metro rail project
Estimates were really high .. even L&T quoted 20% below the estimates.. Hopefully SAM with excellent track record of completing the job on time .. will successfully complete the Kanpur UG Metro.
Hello sir
I am Bijendra pratap Singh
ARO opt in mumbai metro
9473643084
Hello sir I’m Pavan pratap singh land surveyor Gurgaon Central park 2 work experience 3 year contact 7651994892
The difference of 400 crore is too much.it points out that either estimates were wrong or the quality will be compromised.
Wrong comment this copyright
Hope for good quality work @kanpur metro
don’t think they bid it wrong because on same time n same jv team bid Surat metro above the estimate time.
Secondly where gulmerk doing tunneling work going very smooth
. Lucknow metro then pune metro.
May be during pre bid some item get deleted from the station or change of scope..
Hallo Sir.
I am a civil engineer
6 year experiance in industrial construction work.
Hello sir
I am a civil engineer 3 year experience in construction work
Hello Sir,
I am a accountant & Supervisor 6 year experience in RMC Batching Plant.
Hallo sir,
I am a civil supervisor From, STEC Sucgin N
CRTC p4 ANAND VIHAR
Work Experience, 06 years
Hallo Sir.
I am a civil contractor
4 year experiance in industrial construction work.
I am a electrician 2 year experience in gujrat
I am a electrician 2 year experience in gujrat my contact number 7523871345