Gulermak-Sam Starts Soil Testing for Kanpur Metro’s Underground Line

Gulermak – Sam India JV this week began geotechnical soil investigation for Kanpur Metro’s 3.964 km underground section (KNPCC-05) connecting the Ramp at Permat with Nayaganj Station.

An investigation along this route of the 32.385 km Phase 1 project had previously been subcontracted in 2019 by Uttar Pradesh Metro Rail Corporation (UPMRC). This new round of testing with standard penetration tests (SPT) at 36 boreholes is being done to revalidate those findings to help properly design and construct the line’s twin tunnels and stations.

  • Tunnel and Cross-Passages: Investigation is being done at roughly 150m center to center spacing with a drilling depth of 6m (1 times tunnel diameter) below the invert (base) level of the tunnel
  • Ramp and Cut & Cover Portion: 4 boreholes are proposed with a drilling depth of 6m below the rail level
  • Stations: 4 boreholes are planned at each station’s site (Chunniganj, Naveen Market, Bada Chauraha and Nayaganj) with three boreholes of approx. 27m depth and one borehole of 47m depth
Route of Kanpur’s first underground section (Ramp – Nayaganj) with the exact location of stations enroute – view Kanpur Metro route map & information

Here are some snaps from different sites with work by Indian Geotechnical Services getting supervised by the General Consultant TYPSA-Italferr JV‘s personnel (seen in white hard-hats).

Geotechnical works are expected to take about 2 months to get over.

Gulermak – SAM India had received UPMRC’s LOA for Kanpur Metro’s first underground contract in March with a combined value of Rs. 769.23 crore & USD 3.674 million. A tender notice for the second underground section connecting Kanpur Railway Station and Transport Nagar Ramp is currently pending.

For more updates, check out my Home Page!

– TMRG

written by

Global traveler who prefers mass rapid transit

5 Responses to "Gulermak-Sam Starts Soil Testing for Kanpur Metro’s Underground Line"

  1. Clevin Gomes says:

    Estimate was 1400 Crores and their Lowest bid was 1042 Crores, but awarded at 769 Crores. Sounds odd. Why would they negotiate further,if they have bids way less then estimate

    Reply
    • TMRG says:

      Bid was multi-currency. Final contract value is still Rs. 1042 crore (Rs. 769.23 crore PLUS USD 3.674 million)

      Reply
  2. Siddiq Ahmad says:

    HSE ENGINEER

    8004923875

    Reply
  3. There is any vacancy or any chance for civil engineer job says:

    Message me for job

    Reply

Leave a Reply

Want to join the discussion?
Feel free to contribute!

Leave a Reply

Your email address will not be published. Required fields are marked *