Afcons Launches Nagpur Metro Reach 2’s Final Segment

Afcons Infrastructure this weekend celebrated the launch of their final of approximately 2000 segments for constructing Nagpur Metro’s 7.144 km Reach-2 (Sitabuldi – Automotive Square).

This section of the 38.215 km Nagpur Metro Phase 1 project’s Orange Line on Kamptee Road consists of 7 elevated stations and a 4.375 km double decker viaduct which includes a 4 level structure at Gaddigodam Square. Trial Assembly and load testing for its open web girder bridge was in fact just completed last week – see details & snaps.

Route Map of Nagpur Metro’s Reach 2 – view Nagpur Metro map & information

Afcons was awarded a Rs. 573 crore contract for Reach-2 in October 2017 with a 120 week (2.3 year) deadline. Construction work started in November 2017.

With this development, viaduct work on Phase 1 is now pending only at Orange Line Reach-2’s Gaddigodam Railway Crossing and on Aqua Line Reach-4’s 1.6 km Vaishno Devi – Prajapati Nagar section where another double-decker viaduct is being constructed.

For more updates, check out the Nagpur section or my Home Page!

– TMRG

written by

Global traveler who prefers mass rapid transit

9 Responses to "Afcons Launches Nagpur Metro Reach 2’s Final Segment"

  1. Earl Tauro says:

    Just a few days ago, J Kumar has started pending work on the remaining 6 stations of the Navi Mumbai Metro. I have seen workers at RBI and Belapada Stations.m

    Reply
  2. Hanmanthu says:

    TBM oparetor and mechanical engineering

    Reply
  3. Akash says:

    When Nagpur metro phase 2tender opens

    Reply
  4. Akash Gupta says:

    Is any proposed date is Updated for Phase 2

    Reply

Leave a Reply

Want to join the discussion?
Feel free to contribute!

Leave a Reply to TMRG Cancel reply

Your email address will not be published. Required fields are marked *