February 23, 2022 Update: PNC Infratech is lowest bidder – see details.

December 29, 2021 Original Post:14 construction firms have submitted bids to build the 45.244 km Package 2 of the 62.7 km Kanpur – Lucknow Expressway (NE-6) project after the National Highways Authority of India (NHAI) opened technical bids.

This 6 lane access-controlled highway will be upgradeable to 8 lanes and connect Shaheed Path in Lucknow with Azad Marg Chauraha near Kanpur’s Ganga Bridge. Package 2 connecting the town of Bani with Azad Marg Chauraha will be built on a greenfield alignment parallel to the existing NH27.

NHAI invited tenders for its construction under the Hybrid Annuity Mode (HAM) model in September 2021 with a 2.5 year deadline and Rs. 1724.67 crore estimate.

Bidders:

  • APCO Infratech Pvt. Ltd.
  • Ashoka Buildcon Pvt. Ltd.
  • Brij Gopal Construction Co.
  • Dilip Buildcon Ltd.
  • DP Jain and Company Infrastructure Pvt. Ltd.
  • Gawar Construction Ltd.
  • GR Infraprojects Ltd.
  • HG Infra Engineering Ltd.
  • IRB Infrastructure Developers Ltd.
  • Megha Engineering and Infrastructures Ltd.
  • Montecarlo Ltd.
  • Oriental Structural Engineers Pvt. Ltd.
  • PNC Infratech Ltd.
  • Vishwa Samudra Engineering Pvt. Ltd.

Brief Scope: Construction of Six lane upgradable to Eight lane of Kanpur Lucknow Expressway including spur from Km 28+500 to Km 73+744 in the state of Uttar Pradesh on Hybrid Annuity mode under Bharatmala Pariyojana (Package 2)

Kanpur – Lucknow Expressway’s route map (view large) – map via MoEF

All 14 bids have now been sent for technical bid evaluation which can take a couple months to complete. When that is done, the financial bids of the technically qualified bidders will be opened to reveal who’s the lowest bidder and most likely contractor for this package.

In the future, the 594 km Ganga Expressway’s Package 9 (awarded to Adani Enterprises) will intersect Kanpur Lucknow Expressway’s Package 2 in Unnao District.

Back on Monday, NHAI received 16 bids for Package 1 (Amausi – Bani). Design details on the Lucknow-Kanpur Expressway along with a list of all packages and their status can be viewed here.

For more updates, check out the Expressway section or my Home Page!

– TMRG

written by

Global traveler who prefers mass rapid transit

8 Responses to "14 Bidders for Kanpur Lucknow Expressway’s Package 2"

  1. Rajesh says:

    Good information bro…

    Reply
  2. Virendra says:

    Such crores of highways & infrastructure projects are awarded,ongoing & will be awarded in India still experienced highway engineers etc.engg. personal are unemployed looking for jobs.

    Reply
    • M.Sreenivas says:

      well said Brother. But we don’t found and assume the reason behind the unemployed experienced highway engineers.

      Reply
  3. Neeraj bahel says:

    R.N Caterers contector
    79854 20157 83183 74541

    Reply
  4. AK says:

    PNC infratech is L1 for this project…?

    Reply
  5. Jittu says:

    PNC awarded 1 and 2 Package Lucknow kanpur expressway