Kanpur Metro’s Terratec TBM S93 Arrives for Tunneling
Gulermak – Sam India JV last week received tunnel boring machine S93 in Kanpur for tunneling the first 3.619 km section of the 32.4 km Kanpur Metro Phase 1 project’s 8.6 km underground section.
This new 6.52m diameter & 120m long Earth Pressure Balance (EPB) machine passed factory acceptance tests at Terratec’s facility in November 2021. Per the tunneling plan, this machine along with refurbished TBM S92 (details at the bottom) will be deployed on Package KNPCC-05 for a total of 4 drives each:
- Bada Chauraha to Nayaganj: 989.5m
- Permat Ramp’s cut & cover tunnel to Chunniganj: 414m
- Chunniganj to Naveen Market: 748m
- Naveen Market to Bada Chauraha: 516m
Gulermak – Sam India was awarded Package KNPCC-05’s contract by UPMRC in March 2021 with a combined value of Rs. 769.23 crore & USD 3.674 million. Besides tunneling, they will construct 4 station at Chunniganj, Naveen Market, Bada Chauraha and Nayaganj each 215m long.
Gulermak-Sam India’s other TBM S92 passed factory acceptance tests in mid-November in nearby Lucknow. It’s a refurbished machine made through a combination of Lucknow Metro’s S52 & S53 TBMs.
For more updates, check out the Kanpur section or my Home Page! Sign up for free instant email notifications on new posts over here. Like this post? See how you can get early-access to updates and support the site over here.
– TMRG
Any update on Patna metro?
When they will put on the pier caps?
No idea. I’m waiting as well.
Hey TMRG,
What Happened to chennai metro rail corridor no.3 its technical bid is Feb 8 Did they open ?
6 bidders: https://themetrorailguy.com/2022/02/08/6-bidders-for-chennai-metro-line-3s-elevated-omr-section/
Thanks TMRG
Waiting for this news since long time…