L&T’s TBM Shakti Passes Tests for Rishikesh – Karnaprayag Rail Line

Herrenknecht AG on Tuesday completed factory acceptance tests (FAT) on Larsen & Toubro’s first tunnel boring machine, TBM Shakti (S-1309A), for the 125 km Rishikesh-Karnaprayag railway line project’s Package 4.

This new railway line by RVNL will link both towns in Uttarakhand through 12 stations. L&T was awarded a Rs. 3337.60 crore contract for Package 4 in January 2021 to build the section from chainage 47.360 to 63.118.

Package 4 includes 14.577-km up-line and 13.123-km down-line tunnels, out of which 10.490 km and 10.317 km will be constructed using 2 Herrenknecht Hard Rock TBMs with diameters of 9.1 meters. Also included in the scope are a 240m embankment for Devprayag Station, a 300m embankment at Janasu and one minor bridge.

Route of Rishikesh – Karnprayag Rail Line (via RVNL – view large) – view project information

TUMAS India Pvt. Ltd. – Altinok Musavirlik Muhenislik A.S (JV) is Package 4’s detailed design consultant (DDC). Some snaps via Rahul Sharma:

L&T is chasing a 60 month completion deadline. Per their old press release, this will be the biggest TBM to be deployed in the Himalayan region, and the TBM bored tunnel length of 20.807 km will be the longest for any project in the Himalayan region.

Back in January, Herrenknecht completed factory tests on L&T’s first TBM (Marsu) for the 1000 MW Pakal Dul Hydroelectric Project in Jammu & Kashmir – see details and snaps here.

For more updates, check out my Home Page! Sign up for free instant email notifications on new posts over here. Like this post? See how you can get early-access to updates and support the site over here.

– TMRG

written by

Global traveler who prefers mass rapid transit

13 Responses to "L&T’s TBM Shakti Passes Tests for Rishikesh – Karnaprayag Rail Line"

  1. Viraj says:

    Hey TMRG,
    So does L&T usually makes their TBM themselves or Are they new in building TBMs ??

    And if L&T enters into TBM building, Can we say that India wont have to import TBMs in future ??

    Any thoughts ??

    Reply
  2. RAJENDER SINGH says:

    Good & Great job L&T, keep going

    Reply
  3. Kanishka says:

    RVNL e-book; page 41-43 for description of Rishikesh – Karnaprayag New BG Rail Link Project

    https://infocontract.rvnl.org/en/RVNL%20Documents/RVNL%20Book%20-%2017yrs%20of%20Journey.pdf

    Reply
    • Kanishka says:

      125.20 km long railway alignment will have 12 new stations, some of which will be partly inside the tunnels. 105.40 km (84%) of the alignment will pass through 17 tunnels, longest of which is 15.10km long. There will be 17 major bridges, 4 on the river Ganga/Alaknanda.

      – Total Length of tunnels (kms) = 105.47
      – Escape tunnel (Kms) = 98.54
      – Total Length of tunnelling involved (kms) = 218

      Reply
  4. Karanth says:

    Good info on TBM, good to see European machine not other cheap cost one. With L&T being the contractor project will be completed with high quality and on time.

    Reply
  5. Dhiraj kumar says:

    Dhiraj kumar
    RMC BATCHING PLANT OPERATOR S.S. MCI70 ,300,360,370 550 and IDS IBatch mega plus CP 25 CP90, kyb conmat
    Qualification-BA DCA Electronic Diploma
    Job Experience -15 year L&T+HCC
    My Whatsapp n.9696904449

    Reply
  6. Tanishq Bagri says:

    which type of tbm is this ?

    Reply

Leave a Reply

Want to join the discussion?
Feel free to contribute!

Leave a Reply to Kanishka Cancel reply

Your email address will not be published. Required fields are marked *