GR Infra Wins Delhi Mumbai Expressway Jaipur Spur’s Contract

March 30, 2022 Update: NHAI has issued contract LOA to GR Infraprojects.

March 28, 2022 Original Post: GR Infraprojects Ltd. today emerged as the lowest bidder to construct and operate the 67 km Bandikui – Jaipur spur of the 1350 km Delhi – Mumbai Expressway (DME) project.

This 6 lane access-controlled spur’s Detailed Project Report (DPR) was prepared by SA Infrastructure Consultants. Its alignment lies entirely within Rajasthan and will have a 60m right of way (ROW).

The project’s pre-feasibility report can be viewed here, and NHAI’s stated main objective for its development is to reduce the travel time from Delhi-NCR to Jaipur.

National Highways Authority of India (NHAI) invited tenders for its contract in December 2021 with a 1313.82 crore estimate and 910 day (2.5 year) deadline. Technical bids were opened on March 8 to reveal 13 bidders.

Financial Bid Values (Lowest 5):

FirmBid (Rs. crore)
GR Infraprojects1368
Gawar Construction1428
KCC Buildcon1490
Megha Engineering and Infrastructures1556
PNC Infratech1610

Brief Scope: Construction of 6 Lane Greenfield spur from Delhi Vadodara Greenfield expressway near Bandikui to Jaipur in Bharatmala Pariyojana Phase-I on HAM in Rajasthan

Option-2 in Aqua: Selected alignment of Bandikui – Jaipur Spur – view Delhi-Mumbai Expressway project information

GR’s bid of Rs. 1368 crore was just slightly higher than NHAI’s estimate, but well within their permissible limit, so a contract should be awarded in the coming weeks.

Their announcement to the Bombay Stock Exchange (BSE) – view letter – indicates the project will be built in a 4 lane configuration.

As shared earlier, the Delhi-Mumbai Expressway project has a few other spurs in the works:

  • 92 km JNPT spur in Maharashtra. Status: 4/5 tenders have been awarded.
  • 30 km connectivity to Noida’s Jewar International Airport from DND-Faridabad-Ballabhagh Bypass Spur. Status: Current technical bid opening date is April 13.
  • 130 km Ujjain Spur connecting Garoth – Ujjain in Madhya Pradesh. Status: 3 civil contracts awarded.

For more updates, check out the Expressway section or my Home Page! Sign up for free instant email notifications on new posts over here. Like this post? See how you can get early-access to updates and support the site over here.

– TMRG

written by

Global traveler who prefers mass rapid transit

26 Responses to "GR Infra Wins Delhi Mumbai Expressway Jaipur Spur’s Contract"

  1. Abhishek says:

    Wow.. thats quite fast. Technical evaluation completed within 20 days.. or was it not done at all and will be done now after financial bid opening ?

    Reply
    • TMRG says:

      It’s over. Only after technical evaluation do they open financial bids.

      20 days is indeed quite fast. Would love to see same speed in metro projects!

      Reply
      • Anil Hooda says:

        Yes, the Nation needs speedier decision making and implementation.
        For years, we have been rather slow and sluggish.

        Reply
        • AK says:

          Nhai has yearly targets for project award.. normally u will see nhai working hard n fast in march to meet targets of financial year..

          Reply
      • Abhishek says:

        Yeah.. would love too. But then metro constructions involves more technicalities than expressway construction so maybe thats why it takes more time to evaluate technical bids.

        Reply
    • Anil says:

      Financial bids are opened of only those selected bidders who qualify based on technical evaluation.

      Reply
  2. Vc says:

    I think all are seasoned bidders having their qualification already established. I’m guessing that’s the reason for the quick TAT.

    Reply
  3. Yash says:

    Is it going to be 4 or 6 laned , Also please provide the detailed alignment if possible

    Reply
  4. Himanshu gupta says:

    Correct your information about Ujjain spur. All three packages of Ujjain to Garoth 134 Km have been awarded.

    Reply
    • TMRG says:

      Nice, do you have scope and contractor list?

      Reply
      • Himanshu Gupta says:

        Pkg I 4 lane access controlled highway length – 42.15 Km Contractor- GHV India Pvt . Ltd.
        Pkg II 4 lane access controlled highway length length – 47.80 Km Contractor- Ravi Infrabuild projects Pvt. Ltd.
        Pkg III 4 lane access controlled highway length length – 46.35 Km
        Contractor – MKC Infrastructures Ltd.

        Reply
  5. ARVIND JAISWAL says:

    Please also add the spur proposed between Trans Haryana express at Paniala morh to DME at Alwar

    Reply
    • TMRG says:

      Interesting, any more details? Is this the same as Jalbehra-Shahbad (NH-152G) ?

      Reply
      • Himanshu says:

        It will start from where NH-148B(extension of NH152D) ends on the Delhi-Jaipur highway i.e. paniyala mod to Badoda Meo in Alwar district meeting the D-M Expressway there. Road will be of around 86 Kms. Don’t know much about the development since the announcement. Share any news about this if you can!?!

        Reply
  6. primavera p6 says:

    All in all, when the communication is in sync, it makes the overall team collaboration go along smoothly.

    Reply
  7. SNJ says:

    Could you please tell us anything about the consultancy on this project

    Reply
  8. Ramavtar Sharma says:

    Jaipur to bandikui. Mega highway Jahan Bassi tahsil ko thoda Kala gaon mein khasra number 708.705.706.713… ine Kasur ine khatedari jameen mein rasta kata hua Nahin hai fir bhi Highway wale puliya banaa rahe hain aane jaane ke liye kitni jameen Kisan ki kharab ho rahi hai yah unko andaza Nahin hai garibon ka bhi socho Jara.gr Infra walon.. tumhari Khair Nahin hai
    Yah mere mobile number hai 7410 8358 97

    Reply
  9. Tejpal says:

    Sir I am a sub contractor and present time I am working at kannauj in gr nami project drainage work at peti contract but now I want to work on company base contract because I made my own firm so plz sir tell me where I contact to work in bandhikui project

    Reply
  10. Bharat Bhushan Sharma says:

    i have 11 years experience in highway and quality control work and i have been worked with gr infra projects 2016 to 2020 .please provide me jobs .my contact number is 9509973636

    Reply
  11. Amar Singh meena says:

    Sir driver job tm opretor and 1years experience HMV lincesens

    Reply
  12. LAXMAN says:

    Sar main Lakshman Singh railing work ka kam karta hun please kam mujhe hi dewe company ki jo ki let ho aap humse sampark Karen ka mujhe bhi let Ho mere pass ddpil company ki machine hai

    Reply

Leave a Reply

Want to join the discussion?
Feel free to contribute!

Leave a Reply to Bharat Bhushan Sharma Cancel reply

Your email address will not be published. Required fields are marked *