Mumbai Metro’s TBM Tansa-2 Records Breakthrough at Mumbai Central
Tunnel Boring Machine 1239 operated by Doğuş-Soma JV on Tuesday afternoon arrived at Mumbai Central Station on Mumbai Metro’s upcoming 33.5 km Line-3 (Aqua Line).
Nicknamed Tansa 2, this was TBM 1239’s 3nd (and final) breakthrough, and Doğuş-Soma JV’s 5th of 6 breakthroughs planned for package UGC-03 (Worli – Mumbai Central)’s tunnels. Overall, this was Line-3’s 41st of 42 planned TBM breakthroughs.
This Ø6.65m Robbins slurry machine had previously achieved a breakthrough at Mahalaxmi Station in July 2021. It was then was recommissioned in October 2021 for its final assignment to build the 832m down-line tunnel towards Mumbai Central Station.
A video posted by MMRC can be viewed here.
With this development, tunneling for Line-3’s down-line is complete – all the way from Colaba in the south to Sariput Nagar Ramp, near Aarey Colony Station, in the north.
Line-3 now just has 1TBM working from an all time high of 17. A total of 41 breakthroughs have been recorded so far with just 1 more pending – again on Package UGC-03. I’m trying to ascertain Tansa-1’s status and will update this section when I hear something.
Here’s a table displaying UGC-03’s tunneling plan and status of each tunnel (best viewed on a desktop device).
TBM | Line | From | To | Distance | Status |
1 | Up | Science Museum | Worli | 2072m | Completed Jan 2020 |
1 | Down | Science Museum | Mahalaxmi | 1136m | Completed August 2021 |
1 | Up | Mahalaxmi | Mumbai Central | 830m | Ongoing |
2 | Down | Science Museum | Worli | 2057m | Completed March 2020 |
2 | Up | Science Museum | Mahalaxmi | 1118m | Completed July 2021 |
2 | Down | Mahalaxmi | Mumbai Central | 832m | Completed June 2022 (this post!) |
For more updates, check out the Mumbai section or my Home Page! Sign up for free instant email notifications on new posts over here. Like this post? See how you can get early-access to updates and support the site over here.
– TMRG
How much up line tbm remains before last and final breakthrough ?
Trying to ascertain status right now. Will update the post and add a comment here when known 🙂
I heard from Someone that it will take 70/80 days.
Good to know
Hope now with fall of the govt Aarey metro depot construction starts n trail runs can begin
I was also thinking the same thing. Hope all land ssues will be sorted now and also work on bullet train will be fast tracked.
Hi TMRG
Any update on final breakthrough?
Which is the fastest commissioned UG metro in India?