Bids Invited for Kolkata Metro Line-3’s UG1 Underground Contract

Rail Vikas Nigam Ltd. (RVNL) last week invited tenders (bids) for the underground construction work of Kolkata Metro Purple Line’s 5.05 km long Mominpur – Esplanade section (Package UG1).

This northern and final section of the 15.215 km Line-3 (Joka – Esplanade) will consist of twin tunnels running through 4 stations at Kidderpore, Victoria, Park Street and Esplanade. Yuksel Proje – Tumas JV had won its General Consultant (GC) contract in March 2021.

  • Estimated Value: Rs. 2571.28 crore
  • Deadline: Unknown
  • Bid Submission Deadline: 10/10/2022

IFB No: RVNL_Kol2_MTC_JOKA_UG1

Brief Scope: Design and construction of the ramp and underground metro railway works from mominpur (excl.) to esplanade, 5.05 km (from chainage 9063.00m to 14113.00m) including four underground stations (viz. khidderpore, victoria, park street and esplanade), tunnels by tunnel boring machine and cut & cover method, architectural finishing works, track works, etc. in connection with joka-esplanade metro corridor in the city of state of west bengal, india

Indicative alignment and location of stations on Kolkata Metro’s Line-3 – view Kolkata Metro info & route map

The assigned contractor will be required to deploy two new tunnel boring machines (TBMs) with one TBM on stand-by.

Twin tunnels will pass through the Military’s Maidan area, near Fort William, and an agreement on its alignment with Ministry of Defence (MoD) has taken a good 10 years to materialize.

If things go according to the prescribed schedule, then we should see a contractor getting assigned in the 2nd half of 2023, with tunneling work starting in the 2nd half of 2024.

For more updates, check out the Kolkata section or my Home Page! Sign up for free instant email notifications on new posts over here. Like this post? See how you can get early-access to updates and support the site over here.

– TMRG

written by

Global traveler who prefers mass rapid transit

8 Responses to "Bids Invited for Kolkata Metro Line-3’s UG1 Underground Contract"

  1. Gourav Basu says:

    Any update on the progress of the mominpore metro station?

    Reply
  2. Srinu says:

    What about vishakapatnam metro rail

    Reply
  3. Pranay Bhowmik says:

    Really love to see India progressing❤️

    Reply
  4. Avishek Bhattacharjee says:

    Slowest infrastructure project in the country. Neither the public nor the central or state govt seems to be in any hurry to finish the project.

    Reply
  5. Chandan Puitandy says:

    hope it start soon and RVNL prepared for it that don’t be delayed like other metro package in Kolkata.

    Reply
  6. Arnab says:

    Any update on bidders?

    Reply
  7. DILIP KUMAR SINGH says:

    Hello sir namsta
    I am DILIP KUMAR SINGH
    My qualifications is Graduate with gov ITI+ up WAIREMAN PARMITE
    My contact number-9794229229

    Reply
  8. Abhratanu Roy says:

    Any update? Date already gone for bid opening….

    Reply

Leave a Reply

Want to join the discussion?
Feel free to contribute!

Leave a Reply to Abhratanu Roy Cancel reply

Your email address will not be published. Required fields are marked *