Vossloh Wins Bhopal & Indore Metros’ Track Turnout Contract
November 21, 2022 Update: MPMRCL has issued LOA to Vossloh with a contract value of Rs. 37,07,20,108.00
October 16, 2022 Original Post: Vossloh Cogifer earlier this month was declared as the lowest bidder to supply standard gauge rail turnouts (Package BHIN03C) for Indore Metro and Bhopal Metro’s Phase 1 projects.
These turnouts of 60E1 (UIC60) specification will enable both systems’ 52 Alstom trains to guide from one track line to another when sections of each start becoming operational, which I estimate would happen no sooner than mid-2024.
Madhya Pradesh Metro Rail Co Limited (MPMRCL) invited tenders for this contract in February 2022 with a 924 (2.53 year) deadline and unknown estimate.
Financial Bid Values
Firm | Bid (Rs. Crore) |
Vossloh Cogifer | 36.78 |
Voestalpine VAE VKN | 59.82 |
Brief Scope: Design Manufacturing and Supply of Standard Gauge 60 E1_UIC 60_Turnouts for Bhopal Metro Rail Project and Indore Metro Rail Project
MPMRCL’s estimate is unknown to me, so I can’t provide an assessment on the chance of a LOA getting issued to Vossloh.
Both projects have 3 combined rail packages. Here’s the status for each:
BH-IN-03A: Supply of 1260 MT UIC 60 E1 Profile 880 Grade Rails | Jindal Steel & Power Ltd (JSPL) is only bidder |
BH-IN-03B: Supply of 8425 MT Head Hardened Rails | JSPL & Mitsui submitted bids in July 2022 |
BH-IN-03C: Design Manufacturing and Supply of Standard Gauge 60 E1 UIC 60 Turnouts | Vossloh Cogifer is lowest bidder (this post!) |
A list of all Indore Metro and Bhopal Metro’s packages & their status can be viewed here (Indore) and here (Bhopal).
For more updates, check out the Bhopal & Indore sections or my Home Page! Sign up for free instant email notifications on new posts over here. Like this post? See how you can get early-access to updates and support the site over here.
– TMRG