Ranjit Buildcon Ltd. last week poured concrete to cast the very first pier for Ahmedabad Metro Phase 2 project‘s Package C3 connecting Sector-1 – Mahatma Mandir in Gandhinagar.

This pier (P13) is part of the 7.553 km long elevated Package C3 which was awarded to Dilip Buildcon (DBL) in October 2022 with a contract value Rs. 723.45 crore. Construction works were subsequently subcontracted out to Ranjit Buildcon.

Ranjit’s team had started pile load testing works in January 2023 between Sector-1 and Sector 10A and then moved to piling works – the first step of the construction process – at this same site on February 1.

Start of piling works – Photo via Ankush Pal

Package C3 consists of 7 elevated stations at Sachivalaya, Akshardham, Juna Sachivalaya, Sector-16, Sector-24 and Mahatma Mandir.

This is the 3rd and final section of 28.254 km Phase 2 which will see Ahmedabad’s north-south Red Line getting extended by 22.838 km from Motera Stadium to Mahatma Mandir via 20 new stations with a 5.416 km spur from GNLU to GIFT City which includes 2 new stations.

Package C3: Sector-1 – Mahatma Mandir section with indicative location of stations – view Ahmedabad Metro Phase 2 route map & information
Concrete pour underway on Feb 7 – Photo via Arvind Kumar
Casting molds ready to be removed – Photo via Arvind Kumar

For more updates, check out the Ahmedabad section or my Home Page! Sign up for free instant email notifications on new posts over here. Like this post? Get early-access to updates and support the site over here.

– TMRG

written by

Global traveler who prefers mass rapid transit

Leave a Reply

Want to join the discussion?
Feel free to contribute!

Leave a Reply

Your email address will not be published. Required fields are marked *