Delhi-Meerut RRTS Tunnels’ Track-Bed Concreting Work Begins
With the completion of 3 of 6 tunnels on the 82.15 km Delhi – Meerut RRTS project’s Package 8, contractors for this semi high-speed rail project have moved on to the next stage to facilitate system works.
Afcons Infrastructure last week poured first-stage invert concrete inside the down-line tunnel between Begumpul Ramp and Begumpal Station. This work above the tunnels’ precast segment lining is being done to facilitate track-laying work by Larsen & Toubro as part of Package 17.
National Capital Region Transport Corporation (NCRTC) had awarded Afcons with Package 8’s Rs. 1529.10 crore contract in November 2020 with a 1310 day (3.6 year) deadline.
They’ve deployed 3 x 7.51m diameter Terratec Earth Pressure Balance (EPB) machines (S88, S89 & S90) to construct six twin tunnels from Brahampuri DN Ramp to Begumpul UP Ramp. Their scope also includes contructing 3 underground stations at Meerut Central, Bhaisali & Begumpul by cut & cover method.
While concrete works are underway on this section, teams from NCRTC, Afcons and L&T are elsewhere conducting joint tunnel surveys to capture tunnel geometry information using reference points for precise track installation.
In case you missed it – Afcons this month recommissioned tunnel boring machine Sudarshan 8.1 (TBM S88) from Bhaisali Station to Begumpul Station for Package 8’s 5th and penultimate drive.
For more updates, check out the RRTS section or my Home Page! Sign up for free instant email notifications on new posts over here. Like this post? Get early-access to updates and support the site over here.
– TMRG
Meerut city will have three underground stations within the city is it,please let me know.
yes!
Thank you
What about cross passages.How many are there ? Irrespective of desired ROD ,when the civil contractor is likely to complete UG stretch 100%..
I need to check, but believe there are 9 CPs