5 Bidders for Mumbai Metro Line-4’s Track Work Contract CA-161

5 firms have submitted bids to supply and install ballastless tracks for Mumbai Metro’s 32.32 km Line-4 and 2.88 km Line-4A (Green Line) connecting Wadala – Kasarvadavali – Gaimukh through 34 elevated stations.

Tracks from this contract (Package CA-161) will be installed at Line 4 & 4A’s 15.77 km northern section between Mulund Fire Station and Gaimukh. A tender notice for Line-4’s southern section (Wadala – Mulund Fire Station) is still pending.

Mumbai Metropolitan Region Development Authority (MMRDA) had invited bids for this contract in January 2023 with a Rs. 131.11 crore estimate and 2 year installation deadline. Technical bids were opened on Friday.

Bidders

  • Apurvakriti Infrastructure Pvt Ltd.
  • ITD Cementation India Ltd.
  • Paras Railtech Pvt. Ltd.
  • Rahee Infratech Ltd.
  • Texmaco Rail and Engineering Ltd.

Brief Scope: Design, Construction, Manufacturing, Supply, Installation, Testing and Commissioning of Ballastless Trackwork in Mainline from Mulund Fire Station Ch. 18929.611 M to Gaimukh Ch. 34702.272 M including Siding Tracks of Gaimukh Station

Route of Line-4/4A connecting Wadala – Kasarvadavali – Gaimukh – view Mumbai Metro Green Line information & route map with stations

The bids have now been sent for technical evaluation which can take a couple months to complete. When that is done, the financial bids of the technically qualified bidders will be opened to reveal who’s the lowest bidder and most likely track-work contractor.

MMRDA is slowly chipping away at Line-4’s system contracts. Back in February, Jindal Steel & Power Ltd. (JSPL) was declared as the lowest bidder to supply 9800 MT of head-hardened rails.

A list of Mumbai Metro Green Line’s packages (civil & systems) and their status can be viewed here.

For more updates, check out the Mumbai section or my Home Page! Sign up for free instant email notifications on new posts over here. Like this post? Get early-access to updates and support the site over here.

– TMRG

written by

Global traveler who prefers mass rapid transit

One Response to "5 Bidders for Mumbai Metro Line-4’s Track Work Contract CA-161"

  1. AJ says:

    Any update on line 2B’s track work and mandale depot track works?

    Reply

Leave a Reply

Want to join the discussion?
Feel free to contribute!

Leave a Reply

Your email address will not be published. Required fields are marked *