Cengrs Goetechnica on Wednesday started geotechnical soil investigation work for Gurgaon Metro‘s new 28.50 km ring line which will connect HUDA (Millennium) City Centre with DLF Cybercity.

This entirely elevated line with 27 stations in new & old Gurugram was approved for construction by the Indian Government’s Union Cabinet in June 2023. The project will be executed by the newly formed Gurugram Metro Rail Ltd. (GMRL).

Haryana Mass Rapid Transport Corporation Limited (HMRTC) had awarded Cengrs with the line’s first of two geotechnical investigation contracts in February 2024 with a 112 day deadline.

Photo by Cengrs

The scope of Cengrs’ Rs. 53.90 lakh contract includes drilling 130 boreholes, collecting samples, and analyzing the soil’s profile along the line’s 12.76 km alignment between Millennium City Centre to Sector 9.

The results from Cengrs’ investigation will be included within the civil construction tender documents to help infrastructure companies make more informed financial bids and use appropriate machinery, methods & technology during construction.

Photo by Cengrs

The project’s 26.65 km main-line will connect Millennium City Centre and Cybercity via 26 stations, while a small 1.85 km spur will connect Basai Village to Dwarka Expressway with 1 station to provide connectivity to the depot.

Route of HUDA City Centre – Cybercity line – via PIB’s press release
Photo by Cengrs

Earlier this week, HMRTC received just one bid for the line’s Detailed Design Consultant (DDC) contract from SYSTRA MVA Consulting India. It remains to be seen of HMRTC is satisfied or not, but either way the chances of civil construction staring in 2024 are now slim given the time required to prepare detailed designs and to conduct the bidding process for civil construction.

For more updates, check out the Gurgaon section or my Home Page! Sign up for free instant email notifications on new posts over here. Like this post? Get early-access to updates and support the site over here.

– TMRG

written by

Global traveler who prefers mass rapid transit

One Response to "Cengrs Begins Gurugram Metro HUDA – Cyber City Line’s Geotechnical Work"

  1. Pramendra Kumar Khokher says:

    Are they still in doubt about building the metro line that they are not able to do all that panning and preparation stages simultaneously ? What the hell were they doing all this while after the route was finalised last year ? At least they could have got all the preparations done and on file ready to award contract for final construction ? Only in this metro line has so much time (over a decade) been taken and still things are in planning stage and still going around in circles. All those responsible for loss of time and continued suffering of the whole of Gurgaon should be taken to task and some competent people made in charge, otherwise they will bring shame to our PM now

    Reply

Leave a Reply

Want to join the discussion?
Feel free to contribute!

Leave a Reply

Your email address will not be published. Required fields are marked *