Gawar Wins Delhi – Katra Expressway’s Package 18 in J&K
Gawar Construction Ltd. on Friday was declared as the lowest bidder for the civil contract of 650 km Delhi – Amritsar – Katra (DAK) Expressway‘s 15.3 km Package 18 in Jammu & Kashmir.
This 4 lane (expandable to 8) greenfield project by National Highway Authority of India (NHAI) consists of 2 phases. Phase 1 consists of 12 packages for the 397.71 km Delhi – Gurdaspur section and 3 packages for the 99 km Nakodar – Amritsar spur.
Package 18 in Jammu & Kashmir is part of Phase 2 (mostly brownfield upgrade) connecting Gurdaspur – Pathankot – Jammu – Katra. This package involves upgrading the existing national highway NH-44 north of Jammu city between Sidhra and Ban villages into an access-controlled roadway.
The project’s Detailed Project Report (DPR) was prepared by Feedback Infra, and NHAI invited bids for its construction in December 2022 under the Hybrid Annuity Model (HAM) model with a 730 day (2 year) deadline and a Rs. 777.56 crore estimate.
Technical bids were opened in mid-February to reveal 5 bidders.
Financial Bid Values
Firm | Bid (Rs. Crore) |
Gawar Construction Ltd. | 650.99 |
Ram Kumar Contractor Pvt. Ltd. | 691.85 |
Vijay M Mistry Construction Pvt. Ltd. | 734.79 |
APCO Infratech Pvt. Ltd. | 762.23 |
Ceigall India Ltd. | 837.00 |
Brief Scope: Development and Upgradation of Four lane Access Control Expressway from Design Chainage Km 530.000 to Km 545.300 (Sidhra to Ban Village Section of NH-44) of Delhi Amritsar Katra Expressway on EPC Mode under BMP in the UT of JK (Phase II-PKG-XVIII)
Gawar’s bid of Rs. 650.99 crore was well below NHAI’s estimate of Rs. 777.56 crore so a contract should be awarded in the coming weeks.
On the greenfield section (Phase 1), a tender notice for Package 13’s construction near Gurdaspur is still pending. A complete list of Delhi – Katra Expressway’s civil packages and their contractors / status can be viewed here.
For more updates, check out the Expressway section or my Home Page! Sign up for free instant email notifications on new posts over here. Like this post? Get early-access to updates and support the site over here.
– TMRG
Hi sir
I am sr. Structure engg. I have 6 year’s experience. 7988701165
Contect Innova 8968053972
Dear Sir,
I am Banti kumar, Diploma in mechanical engineering with 07 years of experience in field of execution Metro rail projects (Viaduct), Elevated Flyover,ROB and expressway projects.I am presently working at DMIA LAND (INDIA) PVT LTD as an Asst.Manager structure (Erection/Launching) in Rajasthan for Delhi vadodara 8 lane expressway package 10. any vacancies prevailing in your organisation.
Am civil sub contractor. Please contact for structure work PH. 7986100517
Store keeper experience 17yers Afcons Infrastructure &ITD cem
Store Officer experience 17yers Patel Engineering Ltd , Leighton India & ILFS
One year experience Mess supervisor
B tech civil engineer 2 year experience 78 8943 3944 structure
Sir i m bijender kumar. My company GHB infra projects .plz contact earth work and for rent excavator,10 tyre tipper,soil compactor and grader.