Bangalore Metro’s TBM Bhadra Records Breakthrough at K.G. Halli

Tunnel Boring Machine S-840B operated by ITD Cementation India today recorded a breakthrough at Kadugondanahalli (K.G. Halli) Station of the 21.386 km Bangalore Metro Pink Line (Reach 6) project.

Nicknamed Bhadra, this was TBM S-840B’s 3rd of 4 planned breakthroughs and ITD Cem’s 6th of 8 breakthroughs planned for the 73.92 km Bangalore Metro Phase 2 project’s 4.591 km Package RT-04 (Tannery Road – North Ramp).

This Herrenknecht mixed-shield EPB machine was first commissioned from Venkateshpura Station southward to Tannery Road in June 2021. For its latest assignment, it built a 1184m tunnel northward from Venkateshpura to KG Halli boring at an average rate of 3.3m/day through mixed face hard rock conditions.

Here’s a summary of all completed drives:

  • Venkateshpura to Tannery Road (822m): June 2021 – July 2022
  • Tannery Road to Shadi Mahal TBM Retrieval Shaft (222m): July 2022 – December 2022
  • Venkateshpura to Kadugondanahalli (1184m): February 2023 – February 2024
Photo by BMRCL

ITD Cem’s scope of work involves building a combined total of 6.34 km twin tunnels, roughly 360 meter ramp at Nagawara, and four stations at Tannery Road, Venkateshpura, Kadugundanahalli (formerly Arabic College) and Nagawara.

Alignment of ITD Cem’s Package RT-04 – view Bangalore Metro Phase 2 info & route map
Photo by Bala Subramani
Photo by Shiva Shankar

With this development, Bhadra will now be dragged across Kadugondanahalli Station’s box, which can take 20-45 days, and be relaunched for its fourth and final drive of roughly 935m towards Nagawara Station’s southern cut & cover section-1.

Its sister machine, TBM Tunga (S-639B), working on the parallel down-line tunnel had arrived at Kadugondanahalli Station in December 2023 and was re-commissioned earlier this week towards Nagawara. The soil profile of this final section comprises of a mix of weathered rock and sandy silt/clayey sand at shallow depths – making it relatively easier to tunnel through.

Per BMRCL overall tunneling progress for Phase 2 stands at 19.12 / 20.9 km with 24/26 tunnel breakthroughs recorded so far: 8/8 on Package RT-01 by Afcons, 4/4 on RT-02 by L&T, 6/6 on RT-03 by L&T, and 6/8 on RT-04 by ITD Cementation.

For more updates, check out the Bangalore section or my Home Page! Sign up for free instant email notifications on new posts over here. Like this post? Get early-access to updates and support the site over here.

– TMRG

written by

Global traveler who prefers mass rapid transit

6 Responses to "Bangalore Metro’s TBM Bhadra Records Breakthrough at K.G. Halli"

  1. Raghu says:

    Hi TMRG
    When to expect final breakthrough of both the TBM.

    Reply
    • TMRG says:

      Hi, BMRCL’s January newsletter says they’re aiming for May 31 (Tunga) and June 30 (Bhadra), so sometime in Q3 (July – Sept)? Let’s see how things progress

      Reply
  2. Sriharsha says:

    Well what is the position on the trains for this section. Have the orders been placed and do we have a time frame when its expected. It should not be a yellow line situation where we are waiting for over 1 years for the trains to arrive.

    Reply
  3. Gaurav says:

    Hi TMRG

    I reckon the tunnelling for the entire pink line should finish by the end of this year? How long would the station work take in your opinion? When do you expect pink line to be operational?

    Reply
  4. Mafia Muniyappa says:

    40 %. Is a curse on Bangaloreans irrespective of who governs. Let’s hope we will have a fully functional metro system by 20 ! 40 (%).

    Reply

Leave a Reply

Want to join the discussion?
Feel free to contribute!

Leave a Reply

Your email address will not be published. Required fields are marked *