3 Bidders for Bhubaneswar Metro’s Detailed Design Consultant Contract BCDD-02

Three consulting firms have submitted bids for Bhubaneswar Metro Phase 1 project’s Detailed Design Consultant (DDC) contract BCDD-02 after the Delhi Metro Rail Corporation (DMRC) opened technical bids in late-May.

The scope of this contract includes two parts. The first pertains to 26.04 km Line-1’s Phulapokhari Depot and its Operational Control Centre (OCC)’s architectural, electrical & mechanical (E&M), traction and civil works. This facility for servicing 26.04 km Line-1 (Biju Patnaik Airport and Trisulia Square) will be built under Package BBC-02 and a contract to M I A Construction was just awarded on June 14 (see details).

The second part involves proof checking Line-1’s substructure (viaduct), special span (location unknown to me, but likely over Indian Railways’ line on Barang Road), stations and 750V DC traction & power supply works.

DMRC had invited bids for this consultancy contract in March 2024 with a Rs. 22.20 crore estimate and 36 month deadline. Technical bids were opened on May 22.

List below shows lead bidders (some may be in a JV with other partners)

Bidders

  • Ayesa India Pvt. Ltd.
  • Intercontinental Consultants and Technocrats Pvt. Ltd. (ICT)
  • STUP Consultants Pvt. Ltd.

DMRC’s Brief Scope: Engagement of Detail Design Consultant (DDC) for Architectural and Building Services including E&M, Traction works and Civil works for Depot and OCC building including proof checking of substructure for viaduct, special span including its superstructure and stations for from Biju Patnaik Airport to Trisulia Square Phase-I of Bhubaneswar MRTS BMRC, along with 750V DC traction & power supply works for elevated station & depot and RSS works.

Location of Phulapokhari Depot (BBC-02) and stations on Package BBC-05: KIIT Square to Trisulia Square– view Bhubaneswar Metro Map and Information
Grainy image of the depot’s layout included in DMRC’s tender documents

The bids have since late May been undergoing evaluation which can take a couple months to complete. When completed, the financial bids of the technically qualified bidders will be opened to reveal who’s the lowest bidder and most likely consultant.

Technical bids were opened today for the main-line’s construction via packages BBC-03BBC-04 & BBC-05. I’ll share a list of bidders when I get a wind of their names, so stay tuned!

A list of all Bhubaneswar Metro civil & system tenders and their status / contractors can be viewed here.

For more updates, check out the Bhubaneswar Metro section or my Home Page! Sign up for free instant email notifications on new posts over here. Like this post? Get early-access to updates and support the site over here.

– TMRG

written by

Global traveler who prefers mass rapid transit

One Response to "3 Bidders for Bhubaneswar Metro’s Detailed Design Consultant Contract BCDD-02"

  1. Bihari Majdoor says:

    Are babua mainline ka kaam kab chalu hoga? Any idea when the main line work will start? Expected date?

    Reply

Leave a Reply

Want to join the discussion?
Feel free to contribute!

Leave a Reply

Your email address will not be published. Required fields are marked *