RITES Awarded Jaipur Metro Phase 2’s DPR Consultant Contract
RITES Ltd. in November was awarded a Rs. 4.69 crore contract by Jaipur Metro Rail Corporation (JMRC) for reviewing Jaipur Metro Phase 2 project’s Detailed Project Report (DPR), conducting traffic & transport studies for new metro routes, and preparing a DPR of feasible routes.
Jaipur Metro’s Phase 2 project involves constructing a new 23.51 km Orange Line with 21 stations between Ambabari – India Gate (Sitapura Industrial Area). Its DPR was originally prepared in March 2010 and revised several times by the Delhi Metro Rail Corporation (DMRC) and Egis Rail – Feedback Infra JV (which ended in a legal battle), with the latest DPR getting prepared in 2020.
Rajasthan’s Government in 2024 announced the extension of the line from Ambabari northwards towards Vidhyadhar Nagar by approximately 7 km due to which JMRC decided to review the entire project. It now treats Ambabari – Sitapura as Phase 2A and Ambabari – Vidhyadhar Nagar as Phase 2B.
JMRC had invited bids for this consultancy contract in July 2024 with a 120 day contract period. Technical bids were opened on August 5 to reveal 2 bidders – RITES and SYSTRA MVA Consulting (India), and financial bids were opened on August 23 to reveal RITES as the lowest bidder.
Here’s a copy of the LOA:
Deliverables
As part of the contract RITES has 4 deliverables:
- Deliverable 1: Preparation of Detailed Project Report (DPR) for Phase 2 & its extension on the basis of Detailed Traffic & Transport Study and related assessment along operational phases i.e. Phase 1 – Mansarovar to Badi Chaupar, under implementation phases i.e. Phase 1C – Badi Chaupar to Transport Nagar & Phase 1D – Mansarovar to Ajmer Road Chauraha and proposed Phase 2 (Phase 2A + 2B) to identify most viable Phase 2 metro corridor along with other future metro extensions
- Deliverable 2: Preparation of Detailed Project Report (DPR) for most viable and effective metro corridors/extensions etc. identified on the basis of study and approved by the Competent Authority
- Deliverable 3: Preparation of Detailed Proposal for First and Last mile connectivity for all operational and proposed metro stations along with provision of parking in all important metro stations
- Deliverable 4: Prepare a detailed Proposal plan for Value Capture Financing (VCF) by acquiring land parcels of JDA along the metro corridors.
JMRC’s Brief Scope: Selection of Consultancy Firm for Conducting Traffic & Transport Studies for New Metro Routes, Reviewing of Phase. 2 DPR (2020), Preparation for DPR for Feasible / Selected Routes and Other Works
Besides the Orange Line, here’s a list of routes I’ve heard that are being being tabled for inclusion in Phase 2 based on earlier DPRs, government announcements, suggestions and proposals.
- Badi Chaupur to Ajmeri Gate (3 km)
- Transport Nagar to Sanganeri Gate (3 km)
- Mansarovar to Sanganer Police Station on Tonk Road (12 km)
- Ajmer Road Chauraha to Heerapura (3 km)
This is a good restart, but there’s a long…long way to go before we see Phase 2 getting to the construction stage, easily 3 years I’d say and that’s if the Rajasthan government starts getting serious about its execution.
For more updates, check out the Jaipur Metro section or my Home Page! Sign up for free instant email notifications on new posts over here. Like this post? Get early-access to updates and support the site over here.