Mumbai Metro Line 9: Rahee Wins Track Work Contract CA-167
Rahee Infratech was today declared as the lowest bidder to supply and install…
Rahee Infratech was today declared as the lowest bidder to supply and install…
J Kumar Infraprojects (JKIL) on Friday officially started tunnel excavation…
October 18, 2023 Update: Tender has has been canceled by MMRDA. June 10, 2023…
September 26, 2023 Update: MMRDA has awarded LOA contract to Apurvakriti Infrastructure…
LKT Engineering Consultants – Enia Design JV this Monday was declared…
11 firms have submitted a total of 19 bids for the construction work of Mumbai…
February 28, 2024 Update: MMRDA has issued LOA to Paras Railtech with a contract…
Five firms have submitted bids to supply and install ballastless tracks on Mumbai…
October 16, 2023 Update: MMRDA has awarded contract LOA to J Kumar Infra valued…
April 25, 2023 Update: Per the comment section, it appears the contract was…