J Kumar’s Mumbai Metro Line-7A TBM Disha Starts Tunneling

J Kumar Infraprojects (JKIL) on Friday officially started tunnel excavation works for Mumbai Metro Red Line’s 3.17 km Line-7A (Gundavali – CSIA) at Chhatrapati Shivaji International Airport’s Terminal 2 Station.

Workers commissioned the first of two TBMs, T62 nicknamed Disha, a Ø6.68m dual-mode Terratec machine that was previously deployed in 2018-2021 by JKumar – CRTG JV as Tapi-2 to build 3 tunnels for Package UGC-06 of the 33.5 km Line-3 (Aqua Line).

Following its final breakthrough at the Domestic Airport Station in February 2021, T62 was dismantled and taken to J Kumar’s casting yard (view on Google Maps) in Chenna village on Ghodbunder Road for refurbishment.

The machine, now nicknamed as Disha, has been launched to build the approximately 2.49 km up-line tunnel on Package CA-48 from CSIA’s Terminal 2 towards Airport Colony Station and onwards to a ramp on the Western Express Highway (WEH).

Photo by Ittirit Khemasiri

Mumbai Metropolitan Region Development Authority (MMRDA) had awarded J Kumar Infraprojects with Package CA-48’s Rs. 1,998 crore contract in September 2019.

Their scope of work, besides the 11.38 elevated Line-9 extension, includes building Line-7A’s viaduct, ramp and underground tunnels and 2 stations at Airport Colony and CSIA Terminal 2, where it’ll meet the under construction Line-3 (Aqua Line), and in the future Line-8 (Gold Line) linking to Navi Mumbai International Airport.

Indicative Route Map of Mumbai Metro’s Line-7A – view Mumbai Metro map & information

TBM Disha had passed factory acceptance tests (FAT) in January-end 2023 – view images here. Workers began lowering its parts into CSIA Terminal 2 Station’s site in May 2023.

Photo by Ittirit Khemasiri

J Kumar’s team had installed 2 temporary tunnel rings within the shaft in August. A cool video posted by MMRDA with the Disha’s cutterhead rotating can be viewed here on X (Twitter).

TBM Disha (T62) and TBM Dhruv (T60) – Photo by Harish Gaikwad

TBM T60 (Dhruv) for the parallel down-line tunnel is planned to be commissioned in mid-October.

At this time I see Line-7A becoming operational no sooner than mid-2026 looking at the performance of Aqua Line’s TBMs around the airport that I’ve tracked, and the standard system installation and station development work required.

For more updates, check out the Mumbai section or my Home Page! Sign up for free instant email notifications on new posts over here. Like this post? Get early-access to updates and support the site over here.

– TMRG

written by

Global traveler who prefers mass rapid transit

5 Responses to "J Kumar’s Mumbai Metro Line-7A TBM Disha Starts Tunneling"

  1. Rupraj Sengupta says:

    Will it have an passenger interchange with line 3.

    Reply
  2. Sunil says:

    All kinds of connectivity desperately needed for mobility and access in Mumbai. Is there connection with metro-3 and metro-8 underground ?

    Reply

Leave a Reply

Want to join the discussion?
Feel free to contribute!

Leave a Reply

Your email address will not be published. Required fields are marked *