DMRC Revises ITO – Kashmere Gate Line’s Deadline to November 2016

The Delhi Metro Rail Corporation has once again quietly revised the official deadline of the 5.37 km ITO – Kashmere Gate section of the Violet Line to November 2016. In the past they were targeting this section of the 160 km Phase 3 project to open in December 2015, pushed it up to March 2016 and then once again to September. At the start of the year, the line’s Chief Project Manager was chasing an Independence Day (August 15) opening which was substantiated by this internal circular.

Tunneling works on this section, especially the Jama Masjid – Delhi Gate portion was quite challenging and necessitated the use of an additional TBM & mid-shaft at Golcha Cinema in Daryaganj. In March 2016, the contractor for this portion, the L&T-SUCG JV, was finally able achieve the line’s final TBM breakthrough at the Delhi Gate station.

Project Background:

Under the Delhi Metro Phase-III project, the Violet Line is currently being extended by a distance of 9.37 km from Central Secretariat to Kashmere Gate. Out of this, the 3.03 km Central Secretariat – Mandi House stretch became operational on June 26 2014 and the .972 km Mandi House – ITO stretch on June 8 2015 – See: Delhi Metro’s History.


Map of Delhi Metro’s 9.37 km Violet line extension – view Delhi Metro Phase 3 map & information

For construction purposes, the line was divided up into 3 contracts. Here’s a list along with the contractors:

• Contract CC-01 from Central Secretariat to Mandi House: Pratibha – CRFG JV
• Contract CC-05 from Mandi House to Jama Masjid: L&T – SUCG JV
• Contract CC-07 from Jama Masjid to Kashmere Gate: Era – Metrostroy JV

Some new images:


Water proofing works on top of the Delhi Gate station – Photo Copyright: DMRC


Concourse level of Jama Masjid station – Photo Copyright: DMRC


Platform level of Delhi Gate station – Photo Copyright: DMRC


Inside a NATM tunnel leading to Kashmere Gate station – Photo Copyright: Tanmay Chachan

Photo Copyright: Devraj Mahanand

Between Delhi Gate & Jama Masjid stations – Photo Copyright: Devraj Mahanand

For more updates, check out the Delhi section of The Metro Rail Guy!


Share this post!
Share on FacebookTweet about this on TwitterDigg thisShare on LinkedInPin on PinterestShare on RedditShare on Google+Share on StumbleUponShare on TumblrEmail this to someonePrint this page

written by

Global traveler who prefers mass rapid transit

14 Responses to "DMRC Revises ITO – Kashmere Gate Line’s Deadline to November 2016"

  1. Aishwarye says:

    Hi! Till when do you expect the trial runs to begin on this stretch?

    • TMRG says:

      Tough to put a month for trials, especially with DMRC making very last minute announcements in this phase. But I do agree with Aby’s assessment below. There’s a lot pending, both inside & overground. I wouldn’t be surprised if they start trials on a small section (ITO-Delhi Gate) next month in order to establish a milestone for the record and keep the junta satisfied.

  2. Aby says:

    I think it will take another 3 -4 months for trials to begin n another one or two month for operational lots of pending work even work at Kashmiri gate just started

  3. harsh says:

    wonder y dmrc now days is giving false deadlines.

    • TMRG says:

      I wonder why as well. Perhaps the new MD fears criticism as this would be the most delayed phase among all 3? Trial runs so far have been mostly to ‘show’ that things are on track while they clearly aren’t.

  4. Siddhant Kumar says:

    So this line will be ready for passenger operations in november 2016.

  5. Siddhant Kumar says:

    Is the track work completed between lal qila and jama masjid stations.

  6. Siddhant Kumar says:

    Is the track work completed between lal qila and kashmere gate stations.

  7. bipin says:

    When will line to Delhi Gate will Start

  8. naresh k gupta says:

    our self styled efficient and in fact duffer CM should take credit for this inordinate delay. are u listening mr kanjariwal?

  9. amit says:

    November is going to start will the line start operating or again we ur going shift the deadline?