DMRC MD Approves Survey for Modified 95.86 km Phase 4

In December 2015, I shared an official map & plan of what Delhi Metro’s 103.93 km Phase 4 project would look like. That plan has now been modified to a slightly smaller 95.86 km project with multiple changes across key metro lines.

Last week during the multiple TBM breakthroughs at the Mayapuri Shaft & Lal Qila station, I got my hands on a document in which DMRC’s Managing Director has approved survey & preliminary ‘pre-construction’ works on all lines that are currently on the table for Phase 4. These lines have been assigned to different Chief Project Managers (CPMs) with orders to immeadiately start survey & other assorted preliminary works on their allocated corridor. Here’s the document:

Allotment of preliminary work schedule for Phase 4 lines

Allotment of preliminary work schedule for Phase 4 lines

Here’s a list of all the corridors that are on the table:

New Lines – There have been major alignment changes here
Note: I have assigned random line colors to each corridor to highlight them on the map below.

Dwarka – Kanjhawala – Prem Piao: 18.6 km with 18 stations
This is a new line that has been added to the mix. Interestingly both Kanjhawala and Prem Piao do not fall on the route of the new Urban Extension Road (UER) # 2 that is being built to urbanize the north-western part of rural Delhi.

Tughlakabad – Saket – IGI Terminal 1: 19.68 km with 15 stations
This line was earlier envisaged to connect with the Aerocity station, but will now go on to meet the Terminal 1 station with connections at Tughlakabad with the Violet line, Saket with the Yellow line, possibly the Aerocity station of the Airport Express line and finally the Magenta line’s Terminal 1 station.

Majlis Park  – R.K. Ashram: 10.72 km with 10 stations
This line is a truncated version of the Janakpuri W – R.K. Ashram extension of the Magenta line that was planned to come up in Phase 4. With the Janakpuri W to Majlis Park component gone, this corridor will now function as a new stand-alone line with connections to the Blue line at R.K. Ashram, Green line at Nabi Karim, Yellow/Pink line at Azadpur and the Pink line at Majlis Park.

Extension of existing lines – There have been no changes to the alignment

Pink line – Majlis Park – Maujpur: 12.56 km with 6 stations
One of the following 7 stations has been dropped: Burari Crossing, Jagatpur Village, Surghat, Khajuri Khas, Bhajanpura, Yamuna Vihar and Maujpur

Green line
– Inderlok – Indraprastha: 12.57 km with 10 stations
Stations on this corridor include: Inderlok, Dayabasti, Sarai Rohilla, Ajmal Khan Park, Nabi Karim, New Delhi, LNJP Hospital, Delhi Gate, IG Stadium and Indraprastha

Red line
– Rithala – Narela: 21.73 km with 16 stations
Stations on this corridor include: Rohini Sector 26, Rohini Sector 31, Rohini Sector 32, Rohini Sector 36, Rohini Sector 37, Barwala, Put Khurd, Bawana Industrial Area – 1, Bawana Industrial Area – 2, Bawana, Bawana JJ Colony, Sanpath, New Sanath Colony, Anaj Mandi and Narela

Based on the above, here’s a preview of how all 6 corridors might look like:

Phase 3’s construction is expected to end in 2018 after/during which Phase 4’s tendering process will begin. By then, multiple changes in scope, alignment and design are expected to take place, so there’s nothing to be alarmed about. One of those changes in scope would include the addition of a new corridor connecting Dwarka with Gurgaon for which the DMRC was recently tasked to prepare the Detailed Project Project. Whether this will be an extension of the Airport Express line or the Blue line is yet to be seen. There’s still a long, long way to go before Phase 4’s plans are finalized.

For more updates on the Delhi Metro’s project, check out the Delhi section of The Metro Rail Guy!

– TMRG

 

written by

Global traveler who prefers mass rapid transit

50 Responses to "DMRC MD Approves Survey for Modified 95.86 km Phase 4"

  1. VEERAT Marwah says:

    It says dat phase 3 construction is expectd to end in 2018.
    I believe it’s 2016..else…its really a looonnnggggg way to go.

    Reply
    • TMRG says:

      Blue line to Najafgarh & Red line to Ghaziabad will open in 2018, and that will bring Phase 3’s construction to an end. Please see the Delhi section for updates.

      Reply
      • ruchir Bhatia says:

        Red line to ghaziabad will open in 2017 as per Mangu singh yesterday. also do you have any information regarding blues line extension from vaishali to Vasundhara or indirapuram

        Reply
        • TMRG says:

          Hi, opening in 2017 would be great but not possible as per my estimate. The Blue line is not being extended from Vaishali in Phase 3. It’s being extended from Noida City Centre to Noida Sector 62 (NH-24) – please see this map

          Reply
  2. Garudha says:

    Isn’t the Inderlok-Indraprastha a new line given the mess of the existing green line alignment and the fact that all new stations are to be underground (a new underground station just north of the existing red line Inderlok?) Where could they put a depot for this new line, or how could it connect to the existing green line?

    Reply
    • Chronicsurfer says:

      Currently Inderlok Red Line is a T-junction with the Green Line, so if the underground station starts from here, commuters will be forced to change lines here – making the Indraprastha line an independent line.

      Ashoka Park connects to Inderlok and Kirti Nagar… I do not think there is provision currently to extend this line directly on to Rohtak Road and take it underground to Dayabasti and onwards to Indraprastha which will give direct connectivity to Nangloi.

      The Green Line exchange may be messy, it would be interesting to see how they make it!

      Reply
  3. Siddhartha says:

    Dwarka-Prem Piao does not feature on official map for Phase IV. Is that new addition where will it lie, what stations are planned

    Reply
  4. ankit says:

    how much time it will take for the construction of the phase 4 to begin?
    how many station will be their between dwarka and kanjhawla?

    Reply
  5. FLY2 says:

    Has green line extension from kirti Nagar to Dwarka 28 been dropped off?

    Reply
  6. Amit says:

    Has route from janak Puri West along side of outer ring road being dropped?

    Reply
    • TMRG says:

      Yes, the Janakpuri-Pitampura-Haiderpur route has been dropped for now. None of the media houses caught that change.

      Reply
  7. Vinod Kumar says:

    Final DELHI METRO LINE PHASE IV

    Reply
  8. Krishan kumar says:

    Please tell me the details of Metro project from badarpur to igi airport with station that are underground and on the pillars.

    Reply
    • TMRG says:

      Final list of station names are yet to be announced. What is known is that all stations between Saket and IGI will be will underground. A small 2.36 km section of the Tughlakabad-Saket will be underground, so expect 1-2 stations to be underground.

      Reply
  9. Krishan kumar says:

    Saket to tugalkabad name of underground ? stations and name of on the pillars

    Reply
  10. Shovan Patra says:

    There need to to more lines,
    Viz. 1) Khajuri Khas to ISBT (Kashmere Gate)- via. pusta road, Shastri Park, IT Park, ISBT. This may also be done by extending the Faridabad-Kashmere line upto Khajuri Khas.
    2) Majlis Park-Shiv Vihar corridor should be extended to Ankur vihar (UP) via Karawal Nagar
    3) At sangam Vihar, Delhi-62, there should be some line to relief the commuters.

    Reply
  11. yogender narwal says:

    Why Chang metro line by ignou

    Reply
  12. Akshun Khurana says:

    Do you know anything about the line from “Kirti Nagar to Dwarka Sector 10” which was earlier proposed for Delhi Metro Phase 4?

    Reply
    • TMRG says:

      Hi, it’s not being pursued anymore. Would have been an excellent alternative than the longer Blue line. Maybe it’ll come back for Phase 5.

      Reply
      • Chronicsurfer says:

        If only DMRC can realign the Green line extension from Kiri Nagar to Ashoka Park to end at Inderlok, then in future if this line is extended to Dwarka it will be a better alignment and a possible solution to the Green Line mess.

        Reply
      • LALIT SINGH says:

        how many stations between loni border to yamuna bank
        could you tell me please what is the name of loni border station

        Reply
  13. rakesh rohilla says:

    Rithala to narela line. Do metro think villagers will get some benefit of metro cause route is from outside. What about patients who will travel from metro and they wil not get proper connectavity for hospital. Cause of maharshi valmiki hospital station not proposed in 4th phase.

    Reply
  14. Manoj says:

    Is metro route from Badli to Kundli still in plan or dropped?

    Reply
  15. Jaideep says:

    Is there any new development regarding phase 4 esp rithala-Narela line.When do you thinj work will start on these lines

    Reply
  16. RAKESH SHARMA says:

    Living Uttam Nagar, we suggest to link direct Moti Nagar station to Inder Lok at any cost. At present it takes 3 times boarding and a lot of time.

    Reply
    • Chronicsurfer says:

      Absolutely agree. That area through Mayapur Industrial / Lajwanti / Janakpuri is heavily populated. Surprised DMRC did not pick it up in Phase 4.

      Reply
  17. shriya says:

    will burari be a station in pase 4 ?

    Reply
  18. Siddhant bhatia says:

    Hi TMRG,

    Could you please tell me when the metro phase of Rithala to Narela connectivity is to be start?? Is there any news regarding this.

    Thanks!

    Reply
  19. Honey Sharma says:

    Hi TMRG, can you please tell me when will the Shiv Vihar metro station be started ?
    and what are the 6 station in Phase 4 pink line from Maujpur to Majlis park ?

    Reply
    • TMRG says:

      Hi, operations to Shiv Vihar metro station should begin sometime towards middle to end of 2017. The names of the stations have been mentioned above.

      Reply
  20. Sanjay says:

    Is there any proposal of metro to kids an chowk (Gaur chowk) in greater Noida west

    Reply
  21. C S Chawla says:

    What is the exact location of lajpat nagar station under the saket G block to lajpat Nagar line in phase 4

    Reply
  22. Varun Dhasmana says:

    By what date the metro from jasola to botanical garden will function?

    Reply
  23. Anil Kumar says:

    kanjhawala metro project start date confirm

    Reply
  24. Rajnish kumar says:

    Hi TMRG .

    I have 16 openbody trucks and my company name is R.S motors at (loha Mandi )Delhi . I always wanted to work with Delhi metro but i don’t have any link to contact them. many time i checked Delhi metro site for tender but didn’t get any information regarding truck related work tender . If u can give me any detail that where or whom i should talk. Thank you

    Reply
    • TMRG says:

      Hi Rajnish, I don’t have any contacts within the DMRC. My suggestion would be to wait until Phase 4’s civil contracts are awarded which I will write about whenever they are awarded. After that, you can contact the contractor and set something up.

      Reply
  25. amit says:

    Hi TMRG is Dwarka – Kanjhawala – Prem Piao: link is still there in Phase iV plan or its has been leftout from Phase IV plan.

    Reply
  26. Bhatt says:

    Is any proposal for extension of metro from Shiv Vihar to Mandola Vihar, near Tronica City , Ghaziabad

    Reply
  27. parvesh lamba says:

    hi, earlier a station near indira gandhi open university in village neb sarai/ maidangarhi was included and was displayed on the route tughalqabad-aerocity, but i was shocked when i saw the new route on screen displaying saket metro station after metro station of g block – saket. i want to confirm whether any station near ignou is still in the proposal or has been dropped.

    Reply

Leave a Reply

Want to join the discussion?
Feel free to contribute!

Leave a Reply to Sanjay Cancel reply

Your email address will not be published. Required fields are marked *